2259 S OVERLAND AVE 90064

Certificate Information: 2259 S OVERLAND AVE 90064

Application / Permit
22014-10000-05781
Plan Check / Job No.
B22LA23780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) SFD AND 498 SQFT ADDITION TO THE REAR OF SFD. FIRE SPRINKLER REQ'D THRU-OUT
Permit Issued
Issued on 4/18/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2022 APPLICANT
Assigned to Plan Check Engineer 12/2/2022 WEIJIAN HUANG
Corrections Issued 12/5/2022 WEIJIAN HUANG
Building Plans Picked Up 12/6/2022 APPLICANT
Applicant returned to address corrections 2/16/2023 VICTOR CHEN
Plan Check Approved 3/22/2023 DANIEL SMILEY
Issued 4/18/2023 APPLICANT
CofO in Progress 4/22/2026 MICHAEL ALLEN
Permit Finaled 4/28/2026 RICHARD STEINBACH
CofO Issued 4/28/2026 RICHARD STEINBACH
Permit Finaled 4/28/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2023 JASON NG
Grading Pre-Inspection Cleared 2/17/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 2/21/2023 JASON NG

Contact Information

Contractor Affordable Building Solutions Inc; Lic. No.: 1068574-B 8885 SANDALWOOD CT      RANCHO CUCAMONGA, CA 91730
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/2/2023 Corrections Issued JEREMY TODD
Excavation/Setback/Form/Re-Bar 5/2/2023 Approved JEREMY TODD
ELECTRICAL-Rough 5/12/2023 No Access for Inspection HERBERT GIRON
BUILDING-Rough-Frame 5/15/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 5/15/2023 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Barrier 5/15/2023 Approved JOHNNY MIRANDA
METHANE-Rough 5/15/2023 Approved JOHNNY MIRANDA
METHANE-Subgrade 5/15/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/15/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Corrections Issued JEREMY TODD
Pre-Inspection 5/18/2023 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 5/18/2023 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 5/18/2023 Partial Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 5/22/2023 Corrections Issued CLAYTON GRAHAM
Special/Order Compliance 5/22/2023 Not Ready for Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 5/25/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 5/30/2023 Conditional Approval CLAYTON GRAHAM
Footing/Foundation/Slab 5/30/2023 No Access for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 9/15/2023 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 9/15/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 9/15/2023 Not Ready for Inspection ARAM AVEDISIAN
Wood Frame 9/15/2023 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 9/22/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 9/22/2023 Corrections Issued BEN MOLSTAD
Green Building Rough 9/22/2023 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 9/22/2023 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 9/22/2023 Corrections Issued BEN MOLSTAD
Verify Sprinkler Sign Off 9/22/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 9/29/2023 Corrections Issued STEPHANIE SWANSON
Gas Test 9/29/2023 Approved STEPHANIE SWANSON
HVAC-Rough 9/29/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 9/29/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 10/16/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 10/16/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 1/29/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 1/29/2024 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/30/2024 Approved ASHLEY THOMPSON
HVAC-Rough 5/30/2024 Conditional Approval ASHLEY THOMPSON
Interior/Exterior Lathing 5/30/2024 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 6/4/2024 Approved JESUS RODRIGUEZ
Green Building Rough 6/4/2024 Approved JESUS RODRIGUEZ
Shower Pan 6/4/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/4/2024 Approved JESUS RODRIGUEZ
Insulation 6/7/2024 Approved AMY COLIN
Drywall Nailing 6/21/2024 Approved AMY COLIN
ELECTRICAL-Final 4/20/2026 Approved MICHAEL ALLEN
Final 4/20/2026 OK to Issue CofO MICHAEL ALLEN
Footing/Foundation/Slab 4/20/2026 Approved MICHAEL ALLEN
Green Building Final 4/20/2026 Approved MICHAEL ALLEN
HVAC-Final 4/20/2026 Approved MICHAEL ALLEN
PLUMBING-Final 4/20/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 4/20/2026 Approved MICHAEL ALLEN