2259 S OVERLAND AVE 90064
Certificate Information: 2259 S OVERLAND AVE 90064
- Application / Permit
- 22014-10000-05781
- Plan Check / Job No.
- B22LA23780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD AND 498 SQFT ADDITION TO THE REAR OF SFD. FIRE SPRINKLER REQ'D THRU-OUT
- Permit Issued
- Issued on 4/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2022 | WEIJIAN HUANG |
| Corrections Issued | 12/5/2022 | WEIJIAN HUANG |
| Building Plans Picked Up | 12/6/2022 | APPLICANT |
| Applicant returned to address corrections | 2/16/2023 | VICTOR CHEN |
| Plan Check Approved | 3/22/2023 | DANIEL SMILEY |
| Issued | 4/18/2023 | APPLICANT |
| CofO in Progress | 4/22/2026 | MICHAEL ALLEN |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
| CofO Issued | 4/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 2/17/2023 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | JASON NG |
Contact Information
| Contractor | Affordable Building Solutions Inc; Lic. No.: 1068574-B | 8885 SANDALWOOD CT RANCHO CUCAMONGA, CA 91730 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/2/2023 | Corrections Issued | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 5/12/2023 | No Access for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/15/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 5/15/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Barrier | 5/15/2023 | Approved | JOHNNY MIRANDA |
| METHANE-Rough | 5/15/2023 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 5/15/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/15/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Corrections Issued | JEREMY TODD |
| Pre-Inspection | 5/18/2023 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 5/18/2023 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 5/18/2023 | Partial Inspection | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 5/22/2023 | Corrections Issued | CLAYTON GRAHAM |
| Special/Order Compliance | 5/22/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/25/2023 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Partial Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 5/30/2023 | Conditional Approval | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 5/30/2023 | No Access for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 9/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 9/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 9/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 9/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 9/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 9/29/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 9/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/16/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/29/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/29/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/30/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 5/30/2024 | Conditional Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/30/2024 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/7/2024 | Approved | AMY COLIN |
| Drywall Nailing | 6/21/2024 | Approved | AMY COLIN |
| ELECTRICAL-Final | 4/20/2026 | Approved | MICHAEL ALLEN |
| Final | 4/20/2026 | OK to Issue CofO | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/20/2026 | Approved | MICHAEL ALLEN |
| Green Building Final | 4/20/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 4/20/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 4/20/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 4/20/2026 | Approved | MICHAEL ALLEN |