16434 W WESTFALL PL 91436
Certificate Information: 16434 W WESTFALL PL 91436
- Application / Permit
- 22014-10000-05752
- Plan Check / Job No.
- B22LA23682
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* ADDITION TO EXITING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | SELLA BENYAMIN |
| Corrections Issued | 12/27/2022 | SELLA BENYAMIN |
| Quality Review Completed | 12/28/2022 | STEVEN KIM |
| Applicant returned to address corrections | 2/7/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/9/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 4/4/2023 | SELLA BENYAMIN |
| Plan Check Approved | 4/20/2023 | SELLA BENYAMIN |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 8/13/2025 | SEAN WIRCH |
| No Progress | 10/1/2025 | SEAN WIRCH |
| CofO in Progress | 10/1/2025 | SEAN WIRCH |
| CofO in Progress | 3/20/2026 | THOMAS FINNILA |
| Permit Finaled | 3/20/2026 | JOHN JANSON |
| CofO Issued | 3/20/2026 | JOHN JANSON |
| Permit Finaled | 3/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/2/2023 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 3/28/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/29/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Meta Builders Group Inc; Lic. No.: 1100704-B | 15233 VENTURA BLVD SUITE 1210 SHERMAN OAKS, CA 91403 |
| Engineer | Garcia,, Lionel J; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/17/2023 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 6/1/2023 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 6/1/2023 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/20/2023 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 8/22/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/22/2023 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 9/22/2023 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/25/2023 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 10/25/2023 | Partial Approval | SEAN HAUPT |
| Interior/Exterior Lathing | 10/25/2023 | Corrections Issued | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/1/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/1/2023 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 11/1/2023 | Approved | VINCENT HANLEY |
| Insulation | 11/17/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 12/11/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/11/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 12/11/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/9/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 9/9/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 9/9/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 10/22/2024 | Approved | MORRIS JACKSON |
| Final | 10/22/2024 | Corrections Issued | MORRIS JACKSON |
| HVAC-Final | 10/22/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 10/22/2024 | Approved | MORRIS JACKSON |
| Final | 11/15/2024 | Not Ready for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 11/15/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 2/3/2025 | Corrections Issued | JOHN COLEMAN |
| Smoke Detectors | 2/3/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 7/18/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Smoke Detectors | 7/18/2025 | No Access for Inspection | JOHN KIDWELL |
| Final | 8/15/2025 | OK to Issue CofO | SEAN WIRCH |
| Smoke Detectors | 8/15/2025 | Approved | SEAN WIRCH |