427-427 1/2 E 112TH ST 90061

Certificate Information: 427-427 1/2 E 112TH ST 90061

Application / Permit
22014-10000-05747
Plan Check / Job No.
B22LA23656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: ADDITION AND CONVERT SINGLE FAMILY DWELLING TO DUPLEX
Permit Issued
Issued on 2/27/2023
Issuing Office
Current Status
CofO Issued on 3/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 DANIEL YIP
Corrections Issued 12/26/2022 DANIEL YIP
Quality Review Completed 1/4/2023 GARO TELMI
Applicant returned to address corrections 2/14/2023 DANIEL YIP
Plan Check Approved 2/22/2023 DANIEL YIP
Issued 2/27/2023 APPLICANT
CofO in Progress 3/28/2024 ANSON MAGLASANG
Permit Finaled 3/28/2024 ANSON MAGLASANG
Permit Finaled 3/28/2024 ANSON MAGLASANG
CofO Issued 3/28/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/26/2023 TREVOR QUAN
Low Impact Development Cleared 1/26/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/27/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/30/2023 TREVOR QUAN
Sewer availability Cleared 1/30/2023 TREVOR QUAN
SB8 RUD Cleared 2/6/2023 RICHARD TRUONG

Contact Information

Contractor Choe Craig; Lic. No.: 867838-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/19/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 6/29/2023 Approved JOHN KLARIN
PLUMBING-Rough 6/29/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/11/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 7/11/2023 Approved JOHN KLARIN
Green Building Rough 7/11/2023 Approved JOHN KLARIN
HVAC-Rough 7/11/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 7/11/2023 Approved JOHN KLARIN
Insulation 8/1/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 8/1/2023 Approved JOHN KLARIN
Drywall Nailing 8/8/2023 Approved JOHN KLARIN
Green Building Rough 8/8/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 8/21/2023 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 11/16/2023 Approved JOHN KLARIN
HVAC-Rough 11/16/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 11/16/2023 Approved JOHN KLARIN
ELECTRICAL-Final 12/19/2023 Approved JOHN KLARIN
Gas Test 12/19/2023 Approved JOHN KLARIN
HVAC-Final 12/19/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 12/19/2023 Approved JOHN KLARIN
Service/Power Release 12/19/2023 Not Ready for Inspection JOHN KLARIN
Final 1/4/2024 Corrections Issued JOHN KLARIN
Green Building Final 1/4/2024 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Approved JOHN KLARIN
Smoke Detectors 1/4/2024 Approved JOHN KLARIN
Final 2/20/2024 Corrections Issued BEN MOLSTAD
Final 3/1/2024 Corrections Issued BEN MOLSTAD
Final 3/14/2024 Corrections Issued BEN MOLSTAD
Final 3/19/2024 No Access for Inspection BEN MOLSTAD
Final 3/27/2024 OK to Issue CofO ANSON MAGLASANG