12026 W KEARSARGE ST 90049

Certificate Information: 12026 W KEARSARGE ST 90049

Application / Permit
22014-10000-05741
Plan Check / Job No.
B22LA23618
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE PATIO AND ADDITION TO (E) SFD , REBUILD DECK WITH TRELLIS PATIO
Permit Issued
Issued on 2/1/2024
Issuing Office
Valley
Current Status
CofO in Progress on 2/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 CARLOS MONTES
Corrections Issued 1/18/2023 CARLOS MONTES
Quality Review Completed 1/18/2023 KEN GILL
Building Plans Picked Up 1/23/2023 APPLICANT
Applicant returned to address corrections 9/6/2023 CARLOS MONTES
Plan Check Approved 10/16/2023 CARLOS MONTES
Issued 2/1/2024 APPLICANT
CofO in Progress 2/25/2026 HERBERT GIRON
CofO in Progress 3/2/2026 JUAN VALENZUELA
CofO in Progress 3/3/2026 HERBERT GIRON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/9/2023 CATHERINE ADROVER
Grading Pre-Inspection Cleared 7/28/2023 CARLOS MONTES
Low Impact Development Cleared 8/14/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 9/17/2023 AHMED AMARRAGY
GPI Written Notices Cleared 10/16/2023 CARLOS MONTES

Contact Information

Contractor Pomer Construction Inc; Lic. No.: 908354-B 2355 WESTOOD BLVD STE 385      LOS ANGELES, CA 90064
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/6/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 5/10/2024 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/14/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 5/14/2024 Approved CARLOS MATAMOROS
Insulation 5/28/2024 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 5/30/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/30/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 12/30/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 12/30/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/3/2025 Partial Approval JESUS RODRIGUEZ
Deputy Wood Construction 1/6/2025 Conditional Approval JESUS RODRIGUEZ
Insulation 1/15/2025 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 1/15/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 1/16/2025 Partial Approval JESUS RODRIGUEZ
Green Building Rough 1/16/2025 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 1/16/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/16/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/28/2025 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 1/28/2025 Approved JESUS RODRIGUEZ
Insulation 1/28/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/28/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 2/6/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/26/2025 Approved MICHAEL ALLEN
Final 12/26/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 12/26/2025 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/26/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 12/26/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 2/23/2026 Approved HERBERT GIRON
Final 2/23/2026 Corrections Issued HERBERT GIRON
Green Building Final 2/23/2026 Approved HERBERT GIRON
HVAC-Final 2/23/2026 Approved HERBERT GIRON
PLUMBING-Final 2/23/2026 Approved HERBERT GIRON
Service/Power Release 2/23/2026 Approved HERBERT GIRON
Final 3/3/2026 Corrections Issued HERBERT GIRON