1015 N ORLANDO AVE 90069
Certificate Information: 1015 N ORLANDO AVE 90069
- Application / Permit
- 22014-10000-05730
- Plan Check / Job No.
- B22LA23530
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY ADDITION TO EXISTING 1 STORY FAMILY RESIDENCE. ADDITION OF 1,068 SF TOTAL
- Permit Issued
- Issued on 5/4/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | VARAND SARKISIAN |
| Corrections Issued | 11/28/2022 | VARAND SARKISIAN |
| Quality Review Completed | 11/29/2022 | HANS SANTIAGO |
| Building Plans Picked Up | 12/12/2022 | APPLICANT |
| Plan Check Approved | 4/13/2023 | VARAND SARKISIAN |
| Issued | 5/4/2023 | APPLICANT |
| CofO in Progress | 11/20/2025 | ENRIQUE MIRELES |
| Permit Finaled | 11/22/2025 | DEROLD HAUFF |
| CofO Issued | 11/22/2025 | DEROLD HAUFF |
| Permit Finaled | 11/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/30/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 4/4/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/10/2023 | THAN WIN |
Contact Information
| Contractor | Design And Construction Services; Lic. No.: 1071188-B | PO BOX 854 CORONA DEL MAR, CA 92625 |
| Engineer | Hadjian,, Hagop; Lic. No.: C84917 | 23006 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/17/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/15/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 9/25/2023 | No Access for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/9/2024 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/9/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/9/2024 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/14/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 2/14/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 2/14/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 2/23/2024 | Conditional Approval | AMIR NAZARIAN |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 2/23/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 3/20/2024 | Partial Inspection | AMIR NAZARIAN |
| Interior/Exterior Lathing | 5/15/2024 | Partial Approval | AMIR NAZARIAN |
| Insulation | 7/2/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 7/2/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 7/2/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 9/10/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 10/23/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 1/27/2025 | Approved | JOSE MACIAS |
| Deputy Reinf. Concrete | 2/7/2025 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Final | 8/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 8/25/2025 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 8/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/1/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/1/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 10/1/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 10/1/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 10/1/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 10/1/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | ENRIQUE MIRELES |
| Final | 10/30/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Approved | ENRIQUE MIRELES |