14415 W COLLINS ST 91401
Certificate Information: 14415 W COLLINS ST 91401
- Application / Permit
- 22014-10000-05724
- Plan Check / Job No.
- B22LA23501
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 19'-2" X 14' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO (N) 585SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), ALL WORK PER ENG.
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 11/25/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 7/7/2023 | PINANK PATEL |
| Plan Check Approved | 9/10/2023 | LUISANGEL VALENZUELA |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 3/7/2024 | RYAN SALAZAR |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/24/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/24/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/1/2023 | RIDWAN HARDY |
Contact Information
| Architect | , ; Lic. No.: C37162 | , |
| Contractor | Owner-Builder | , |
| Engineer | Azarbin,, Hamid; Lic. No.: NA64515 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/16/2023 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Rough | 10/16/2023 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/19/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/17/2023 | Conditional Approval | RYAN SALAZAR |
| Green Building Rough | 11/17/2023 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 11/17/2023 | Corrections Issued | RYAN SALAZAR |
| Wood Frame | 11/17/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 12/13/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/13/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/6/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/6/2024 | Approved | RYAN SALAZAR |
| Final | 3/6/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 3/6/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 3/6/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 3/6/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 3/6/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 3/6/2024 | Approved | RYAN SALAZAR |