2404 S WILSON AVE 90291
Certificate Information: 2404 S WILSON AVE 90291
- Application / Permit
- 22014-10000-05719
- Plan Check / Job No.
- B22LA23485
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 13'-3" x 30' RECREATION/POWDER ROOM TO A BEDROOM AND FULL BATHROOM AND TO BE PART OF THE (E) S.F.D. WITH AN 12'-2" x 10'-1" ADDITION. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2022 | ALFRED RAMIREZ |
| Corrections Issued | 11/29/2022 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 2/7/2023 | MADISON ODELL |
| Plan Check Approved | 5/10/2023 | MADISON ODELL |
| Issued | 5/10/2023 | APPLICANT |
| CofO in Progress | 6/27/2023 | EVAN COOPER |
| Permit Finaled | 6/29/2023 | DANIEL ORRANTE |
| CofO Issued | 6/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/19/2023 | JENSON LEE |
| Sewer availability | Cleared | 1/19/2023 | JENSON LEE |
| Specific Plan | Cleared | 1/25/2023 | EDUARDO HERMOSO |
| Miscellaneous | Cleared | 1/26/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 1/26/2023 | YINGSHI HUANG |
| ZI | Cleared | 1/26/2023 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2023 | JENSON LEE |
| Waste Hauler Permit | Cleared | 2/7/2023 | WILLIAM AVERETT |
| Coastal Zone | Cleared | 2/16/2023 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 2/16/2023 | LOUIS ORTEGA |
| Specific Plan | Cleared | 2/16/2023 | LOUIS ORTEGA |
| ZA Case | Cleared | 2/16/2023 | LOUIS ORTEGA |
| ZI | Cleared | 2/16/2023 | LOUIS ORTEGA |
| Construction near power lines | Cleared | 5/5/2023 | TINA MIRANDA |
Contact Information
| Architect | Hertz,, David Randall; Lic. No.: NA25190 | , |
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2023 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 5/15/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/15/2023 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 5/15/2023 | Approved | EVAN COOPER |
| Deputy Wood Construction | 5/16/2023 | Conditional Approval | EVAN COOPER |
| Insulation | 5/17/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 5/17/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 5/19/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 6/12/2023 | Approved | EVAN COOPER |
| Final | 6/12/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/12/2023 | Approved | EVAN COOPER |
| HVAC-Final | 6/12/2023 | Approved | EVAN COOPER |
| METHANE-Barrier | 6/12/2023 | Approved | EVAN COOPER |
| METHANE-Subgrade | 6/12/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/12/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/12/2023 | Approved | EVAN COOPER |
| Final | 6/26/2023 | OK to Issue CofO | EVAN COOPER |