10575 W TROON AVE 90064
Certificate Information: 10575 W TROON AVE 90064
- Application / Permit
- 22014-10000-05709
- Plan Check / Job No.
- B22LA23475
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITON AND REMODELING TO SFD.
- Permit Issued
- Issued on 12/15/2023
- Issuing Office
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | JOE VO |
| Corrections Issued | 12/24/2022 | JOE VO |
| Quality Review Completed | 12/27/2022 | GARO TELMI |
| Plan Check Approved | 11/15/2023 | JOE VO |
| Issued | 12/15/2023 | APPLICANT |
| CofO in Progress | 6/30/2025 | STEPHANIE SWANSON |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
| CofO Issued | 7/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/28/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 3/30/2023 | ALESSANDRO MERCURI |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2023 | KEVIN AVILA |
| Sewer availability | Cleared | 4/22/2023 | KEVIN AVILA |
| Construction near power lines | Cleared | 8/8/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/11/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/6/2023 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/18/2024 | Conditional Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/20/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/23/2024 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 10/3/2024 | Partial Approval | REGINA MENDEZ |
| BUILDING-Rough-Frame | 11/13/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | ASHLEY THOMPSON |
| Rough-Elec/Plmb/HVAC | 11/13/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Deputy Wood Construction | 11/20/2024 | Conditional Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 11/20/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 11/20/2024 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 11/27/2024 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 12/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/3/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/5/2024 | Partial Approval | BOBBY KEY |
| Insulation | 12/13/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/13/2024 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 12/13/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/23/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/23/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/25/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 4/25/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/25/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 4/25/2025 | Approved | ARAM AVEDISIAN |
| Final | 6/30/2025 | OK to Issue CofO | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/30/2025 | Approved | STEPHANIE SWANSON |