2525 N BRIARCREST ROAD 90210
Certificate Information: 2525 N BRIARCREST ROAD 90210
- Application / Permit
- 22014-10000-05702
- Plan Check / Job No.
- B22LA23470
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan NEW ATTACHED REC ROOM 740 SQFT ADDITION CONNECTED WITH A SOLID BREEZEWAY (10' WIDTH). TOTAL GRADING NOT TO EXCEED 50 CY
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | JAD BASMA |
| Corrections Issued | 11/26/2022 | JAD BASMA |
| Quality Review Completed | 12/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 5/2/2023 | JAD BASMA |
| Applicant returned to address corrections | 5/4/2023 | JAD BASMA |
| Plan Check Approved | 5/25/2023 | JAD BASMA |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 5/4/2024 | RAUL BARAJAS |
| Permit Finaled | 5/7/2024 | RONALD MYRICK |
| Permit Finaled | 5/7/2024 | RONALD MYRICK |
| CofO Issued | 5/7/2024 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/30/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2023 | DINAH GARIN |
| Sewer availability | Cleared | 1/4/2023 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 1/19/2023 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 1/27/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 2/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/15/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 5/15/2023 | OLGA AYALA |
| GPI Written Notices | Cleared | 5/18/2023 | JAD BASMA |
Contact Information
| Contractor | Miller Kirk Construction; Lic. No.: 377173-B | , |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/13/2023 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/1/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/9/2023 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Rough | 8/16/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/22/2023 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/23/2023 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 10/4/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/6/2023 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 11/7/2023 | Conditional Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 11/13/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/13/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 11/13/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 11/29/2023 | Approved | RAUL BARAJAS |
| Insulation | 11/29/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/29/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/21/2023 | Approved | RAUL BARAJAS |
| Shower Pan | 12/21/2023 | Approved | RAUL BARAJAS |
| Final | 4/4/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 4/4/2024 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 4/4/2024 | Approved | RAUL BARAJAS |
| Final | 5/3/2024 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 5/3/2024 | Approved | RAUL BARAJAS |