1669 W 252ND ST 90710

Certificate Information: 1669 W 252ND ST 90710

Application / Permit
22014-10000-05697
Plan Check / Job No.
B22LA23461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan; 2nd STORY ADDITION AND INTERIOR STR. REMODEL TO (E) 1-STORY SFD.
Permit Issued
Issued on 5/3/2023
Issuing Office
Current Status
CofO Issued on 3/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 MAHNAZ NOURHASHEMI
Corrections Issued 12/23/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 1/6/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/20/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 4/26/2023 MAHNAZ NOURHASHEMI
Issued 5/3/2023 APPLICANT
CofO in Progress 3/22/2024 EUGENE CASSIDY
Permit Finaled 3/28/2024 ANSON MAGLASANG
Permit Finaled 3/28/2024 ANSON MAGLASANG
CofO Issued 3/28/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/13/2023 HUGO LOPEZ
Low Impact Development Cleared 2/27/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 3/1/2023 ANA SORIANO
Sewer availability Cleared 3/2/2023 ANA SORIANO
Hold Cleared 6/26/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2023 Approved EUGENE CASSIDY
METHANE-Barrier 7/5/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 7/5/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 8/25/2023 Conditional Approval ANSON MAGLASANG
Deputy Wood Construction 8/29/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/30/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 8/30/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 8/30/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/28/2023 Approved EUGENE CASSIDY
HVAC-Rough 9/28/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 9/28/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/2/2023 Approved EUGENE CASSIDY
Green Building Rough 10/2/2023 Approved EUGENE CASSIDY
Insulation 10/16/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/16/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 10/23/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/6/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/10/2024 Not Ready for Inspection EUGENE CASSIDY
Final 1/10/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 1/10/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 1/10/2024 Not Required EUGENE CASSIDY
Smoke Detectors 1/10/2024 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 1/10/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 2/14/2024 Approved EUGENE CASSIDY
Final 2/14/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 2/14/2024 Approved EUGENE CASSIDY
Smoke Detectors 2/14/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 2/14/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/11/2024 Approved EUGENE CASSIDY
Final 3/11/2024 Corrections Issued EUGENE CASSIDY
HVAC-Final 3/11/2024 Approved EUGENE CASSIDY
PLUMBING-Final 3/11/2024 Approved EUGENE CASSIDY
Final 3/22/2024 OK to Issue CofO EUGENE CASSIDY