2633 S VINEYARD AVE 90016

Certificate Information: 2633 S VINEYARD AVE 90016

Application / Permit
22014-10000-05693
Plan Check / Job No.
B22LA23452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) 1-STORY ADDITION TO THE REAR OF THE (E) SFD PER ENGINEER DESIGN
Permit Issued
Issued on 10/20/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 WEIJIAN HUANG
Corrections Issued 11/28/2022 WEIJIAN HUANG
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 1/27/2023 LUKE GONZALES
Plan Check Approved 2/1/2023 STANLEY RAAP
Issued 10/20/2023 APPLICANT
CofO in Progress 8/11/2025 ARTHUR NEGRETE
Permit Finaled 8/24/2025 DEROLD HAUFF
CofO Issued 8/24/2025 DEROLD HAUFF
Permit Finaled 8/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/15/2022 AMAAN MALIK
Low Impact Development Cleared 1/25/2023 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/27/2023 AMAAN MALIK

Contact Information

Contractor Molinas Construction Services; Lic. No.: 1091636-B 223 S SENTOUS AVENUE      WEST COVINA, CA 91792
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2023 Conditional Approval CALEB MEISTER
Footing/Foundation/Slab 10/27/2023 Not Ready for Inspection CALEB MEISTER
Pre-Inspection 10/31/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval RONNIE MINDANAO
PLUMBING-Rough 11/8/2023 Conditional Approval CHARLES BOGHOSKHAN
Insulation 11/14/2023 Partial Approval CHARLES BOGHOSKHAN
Wood Frame 11/20/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 4/26/2024 Partial Approval JUSTIN HAWLEY
ELECTRICAL-Rough 4/26/2024 Approved JUSTIN HAWLEY
HVAC-Rough 4/26/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 4/26/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 5/3/2024 Approved JUSTIN HAWLEY
Green Building Rough 5/3/2024 Approved JUSTIN HAWLEY
HVAC-Rough 5/3/2024 Approved JUSTIN HAWLEY
Insulation 5/3/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 5/3/2024 Partial Approval JUSTIN HAWLEY
MERV13>=Rough 5/3/2024 Approved JUSTIN HAWLEY
Drywall Nailing 5/14/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 7/5/2024 Approved JUSTIN HAWLEY
Shower Pan 7/5/2024 Approved JUSTIN HAWLEY
Final 11/27/2024 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready JUSTIN HAWLEY
ELECTRICAL-Final 12/17/2024 Corrections Issued JUSTIN HAWLEY
Special/Order Compliance 12/17/2024 Corrections Issued JUSTIN HAWLEY
Final 1/17/2025 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 1/17/2025 Approved JUSTIN HAWLEY
Green Building Final 1/17/2025 Approved JUSTIN HAWLEY
MERV13>=Final 1/17/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 1/17/2025 Approved JUSTIN HAWLEY
Special/Order Compliance 1/17/2025 Corrections Issued JUSTIN HAWLEY
Service/Power Release 1/28/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Final 8/8/2025 Approved ARTHUR NEGRETE
Final 8/8/2025 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 8/8/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 8/8/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved ARTHUR NEGRETE