12332 W HAVELOCK AVE 90230

Certificate Information: 12332 W HAVELOCK AVE 90230

Application / Permit
22014-10000-05655
Plan Check / Job No.
B22LA23283
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST AND 2ND FLOOR ADDITION TO (E) ONE STORY GARAGE (20 FT X 30 FT ), CONVERT (E) DETACHED GARAGE TO (N) ADU OVER (N) JADU AND 1-CAR GARAGE.
Permit Issued
Issued on 4/4/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 TSE MING HUANG
Corrections Issued 11/29/2022 TSE MING HUANG
Quality Review Completed 12/2/2022 KEN GILL
Building Plans Picked Up 12/5/2022 APPLICANT
Plan Check Approved 3/29/2023 TSE MING HUANG
Issued 4/4/2023 APPLICANT
CofO in Progress 7/17/2024 RICHARD STEINBACH
Permit Finaled 7/17/2024 DANIEL ORRANTE
CofO Issued 7/17/2024 DANIEL ORRANTE
Permit Finaled 7/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/4/2023 ANTHONY MAINEZ
Specific Plan Cleared 1/26/2023 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 2/1/2023 ANTHONY MAINEZ
Sewer availability Cleared 2/1/2023 ANTHONY MAINEZ
Hydrant and Access approval Cleared 2/10/2023 KURT CORRAL
Construction near power lines Cleared 2/27/2023 RIDWAN HARDY
Construction within easement Cleared 2/27/2023 RIDWAN HARDY
Low Impact Development Cleared 3/20/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/31/2023 DINAH GARIN

Contact Information

Contractor American Valley Builders Co; Lic. No.: 1088695-B 19136 VANOWEN STREET      RESEDA, CA 91335
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2023 Partial Inspection HERBERT GIRON
Pre-Inspection 4/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Drilled-In Anchors 4/25/2023 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/28/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 4/28/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/3/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/3/2023 Partial Approval JESUS RODRIGUEZ
Sewer 5/3/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Corrections Issued JESUS RODRIGUEZ
Deputy Wood Construction 6/13/2023 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/3/2023 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 7/3/2023 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 7/3/2023 Approved JESUS RODRIGUEZ
Shower Pan 7/3/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/10/2023 Conditional Approval HERBERT GIRON
Insulation 7/11/2023 Corrections Issued HERBERT GIRON
Insulation 7/14/2023 Approved HERBERT GIRON
Drywall Nailing 8/7/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/7/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/4/2023 Approved JESUS RODRIGUEZ
Final 12/4/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 12/4/2023 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Rough 12/4/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 12/4/2023 Not Ready for Inspection JESUS RODRIGUEZ
Final 1/5/2024 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Final 1/5/2024 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 1/5/2024 Not Ready for Inspection JESUS RODRIGUEZ
Final 1/10/2024 Not Ready for Inspection HERBERT GIRON
Green Building Final 1/10/2024 Not Ready for Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 1/10/2024 Not Ready for Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Not Ready JESUS RODRIGUEZ
ELECTRICAL-Final 5/22/2024 Approved JESUS RODRIGUEZ
Final 5/22/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 5/22/2024 Approved JESUS RODRIGUEZ
HVAC-Final 5/22/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/22/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 5/22/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 5/22/2024 Approved JESUS RODRIGUEZ
Final 7/12/2024 OK to Issue CofO JESUS RODRIGUEZ