4552 N ETHEL AVE 91604
Certificate Information: 4552 N ETHEL AVE 91604
- Application / Permit
- 22014-10000-05607
- Plan Check / Job No.
- B22LA23032
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan -ADDITION AND REMODELLING. NEW 1ST. FLOOR ADDITION - NEW DINING ROOM, NEW BATH ROOM, NEW PORCH, NEW KITCHEN AND ENLARGE EXISTING LIVING ROOM. NEW 2ND. STORY (1.088 SQ. FT.) - NEW 2 BEDROOMS, MASTER BATH, MASTER CLOSET & FAMILY ROOM AND DECK.
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | SAM CHANG |
| Corrections Issued | 1/6/2023 | SAM CHANG |
| Quality Review Completed | 1/10/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 4/6/2023 | SAM CHANG |
| Applicant returned to address corrections | 4/18/2023 | SAM CHANG |
| Plan Check Approved | 4/26/2023 | SAM CHANG |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
| CofO Issued | 4/11/2024 | RUBEN SALAS |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/13/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/14/2023 | CARLOS AGUILERA |
| CPC | Cleared | 2/23/2023 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 3/4/2023 | KURT CORRAL |
Contact Information
| Contractor | C B Home Construction; Lic. No.: 961219-B | , |
| Contractor | C B Home Inc; Lic. No.: 961219-B | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: NA35693 | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/25/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/5/2023 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 6/13/2023 | Partial Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 6/13/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/15/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 8/31/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/6/2023 | Conditional Approval | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/12/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 9/27/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 10/2/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 10/2/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/4/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Gas Test | 12/4/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 12/4/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 12/28/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 12/28/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/28/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/28/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 1/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2024 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Final | 3/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 3/15/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 3/21/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/26/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |