5757 N MATILIJA AVE 91401

Certificate Information: 5757 N MATILIJA AVE 91401

Application / Permit
22014-10000-05595
Plan Check / Job No.
B22LA22964
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) addition to (E) SFD
Permit Issued
Issued on 1/23/2023
Issuing Office
Metro
Current Status
CofO in Progress on 3/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/14/2022 APPLICANT
Assigned to Plan Check Engineer 11/14/2022 KHUONG TRUONG
Corrections Issued 11/14/2022 KHUONG TRUONG
Plan Check Approved 1/23/2023 JOSEPH RAFOLS
Issued 1/23/2023 APPLICANT
CofO in Progress 3/9/2026 JOSE AVILA

Permit Application Clearance Information

Sewer availability Cleared 1/13/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/23/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/23/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/24/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 1/25/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 2/6/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 2/6/2023 Order to Comply Issued RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Approved RYAN SALAZAR
Insulation 2/10/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 3/10/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/5/2023 Approved RYAN SALAZAR
HVAC-Rough 4/5/2023 Approved RYAN SALAZAR
PLUMBING-Rough 4/5/2023 Approved RYAN SALAZAR
Insulation 5/2/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/2/2023 Approved RYAN SALAZAR
Drywall Nailing 5/5/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 1/29/2024 Approved DAVID MATSON
Final 1/29/2024 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 1/29/2024 Approved DAVID MATSON
Green Building Final 1/29/2024 Approved DAVID MATSON
Green Building Rough 1/29/2024 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Not Ready DAVID MATSON
Smoke Detectors 1/29/2024 Corrections Issued DAVID MATSON
Final 1/30/2026 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 1/30/2026 Approved VINCENT HANLEY
Final 3/6/2026 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved JOSE AVILA