6721 S 4TH AVE 90043
Certificate Information: 6721 S 4TH AVE 90043
- Application / Permit
- 22014-10000-05582
- Plan Check / Job No.
- B22LA22929
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Two story ADU addition to existing one-car garage per ordinance
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- Issued on 9/19/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2023 | SHANGQIN XIE |
| Corrections Issued | 2/7/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/10/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 5/18/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/2/2023 | MINA HABILI |
| Plan Check Approved | 9/17/2023 | KHUONG TRUONG |
| Issued | 9/19/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2023 | AMAAN MALIK |
| Construction within easement | Cleared | 4/28/2023 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 5/12/2023 | MARCO SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/16/2023 | JEANIE LAM |
| Sewer availability | Cleared | 5/16/2023 | JEANIE LAM |
| Flood clearance | Cleared | 8/31/2023 | ABDULRAHMAN ALABTAH |
Contact Information
| Contractor | Goliath Construction; Lic. No.: 1056541-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/27/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/28/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| FLOOD-Elevation Certificate | 9/28/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/28/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 10/4/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Approved | JOSE MACIAS |
| Deputy Other (see comments) | 4/2/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 4/3/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 4/3/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/4/2024 | Partial Approval | ANTHONY EGSON |
| Gas Test | 4/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/10/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 4/10/2024 | Approved | JOSE MACIAS |
| Insulation | 4/17/2024 | Approved | JOSE MACIAS |
| Insulation | 4/19/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 4/19/2024 | Approved | CRAIG DAVIS |
| Shower Pan | 4/19/2024 | Approved | CRAIG DAVIS |
| Drywall Nailing | 4/23/2024 | Approved | JOSE MACIAS |
| Gas Test | 6/6/2024 | No Access for Inspection | JOSE MACIAS |
| Underground Mechanical | 6/6/2024 | No Access for Inspection | JOSE MACIAS |
| Gas Test | 6/11/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 6/11/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 7/18/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 8/8/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 8/8/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 8/8/2024 | Not Ready for Inspection | JOSE MACIAS |
| Special/Order Compliance | 8/8/2024 | Partial Inspection | ALEX COLIN |
| Service/Power Release | 11/26/2025 | Not Ready for Inspection | LUIS CASTRO |