10364 S BEACH ST 90002
Certificate Information: 10364 S BEACH ST 90002
- Application / Permit
- 22014-10000-05570
- Plan Check / Job No.
- B22LA22907
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* ADD 14' X 18'-7" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/23/2023
- Issuing Office
- Current Status
- CofO Issued on 2/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2022 | SELLA BENYAMIN |
| Corrections Issued | 11/21/2022 | SELLA BENYAMIN |
| Plan Check Approved | 12/27/2022 | SELLA BENYAMIN |
| Issued | 2/23/2023 | APPLICANT |
| CofO in Progress | 2/28/2025 | ANSON MAGLASANG |
| Permit Finaled | 2/28/2025 | ANSON MAGLASANG |
| CofO Issued | 2/28/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 12/9/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2022 | JEANIE LAM |
| Sewer availability | Cleared | 12/14/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/30/2023 | Partial Approval | JOHN KLARIN |
| Underground Mechanical | 11/22/2023 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 11/28/2023 | Corrections Issued | JOHN KLARIN |
| Deputy Drilled-In Anchors | 11/30/2023 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 1/8/2024 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 1/8/2024 | Approved | JOHN KLARIN |
| Insulation | 1/31/2024 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 1/31/2024 | Approved | JOHN KLARIN |
| Drywall Nailing | 2/8/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 11/19/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 11/19/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/19/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 11/19/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 11/19/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 11/19/2024 | Approved | ANTHONY EGSON |
| Final | 2/28/2025 | OK to Issue CofO | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | ANSON MAGLASANG |