2144 W RIDGEVIEW AVE 90041
Certificate Information: 2144 W RIDGEVIEW AVE 90041
- Application / Permit
- 22014-10000-05545
- Plan Check / Job No.
- B22LA22770
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN- Existing detached garage to be converted into ADU with 16'2" x 39'6" addition at the rear. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | NGHI SU |
| Corrections Issued | 12/13/2022 | NGHI SU |
| Quality Review Completed | 12/15/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/21/2023 | NGHI SU |
| Plan Check Approved | 5/18/2023 | NGHI SU |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 7/8/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 12/13/2022 | NGHI SU |
| Address approval | Cleared | 1/25/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2023 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 1/25/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/25/2023 | ABEL CASILLAS |
| Construction near power lines | Cleared | 4/15/2023 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 4/18/2023 | ISMAEL HERNANDEZ |
| Grading Pre-Inspection | Cleared | 4/24/2023 | NGHI SU |
Contact Information
| Contractor | Lopez Nelson Gacula; Lic. No.: 913712-B | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: L6762 | 2160 PARNELL WY ALTADENA, CA 91001 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/31/2023 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Partial Approval | CRAIG VAUGHAN |
| Pre-Inspection | 8/7/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/18/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/18/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 11/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/28/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/1/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/2/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/2/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 1/2/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/9/2024 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 1/10/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 1/19/2024 | Approved | CHARLES BOGHOSKHAN |
| Sewer | 2/9/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Sewer | 2/14/2024 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 2/14/2024 | Partial Approval | CRAIG VAUGHAN |
| Final | 6/25/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 6/25/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 6/25/2024 | Approved | BRIAN SULLIVAN |
| Final | 7/5/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 7/8/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |