3346 E LOOSMORE ST 90065
Certificate Information: 3346 E LOOSMORE ST 90065
- Application / Permit
- 22014-10000-05537
- Plan Check / Job No.
- B22LA22726
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. NEW ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING. NEW UNCOVERED DECK.
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | KEVIN MORALES |
| Corrections Issued | 11/29/2022 | KEVIN MORALES |
| Quality Review Completed | 11/29/2022 | EUGENE BARBEAU |
| Plan Check Approved | 8/24/2023 | KEVIN MORALES |
| Issued | 8/24/2023 | APPLICANT |
| CofO in Progress | 5/13/2024 | OSVALDO PARAMO |
| Permit Finaled | 5/15/2024 | DEROLD HAUFF |
| CofO Issued | 5/15/2024 | DEROLD HAUFF |
| Permit Finaled | 5/15/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/19/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 1/27/2023 | KIRK LINKLATER |
| Supp. Use District POD/CDO/TDO | Cleared | 8/22/2023 | DANIEL CORONADO |
Contact Information
| Contractor | Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Approved | OSVALDO PARAMO |
| Insulation | 9/20/2023 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 9/20/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/7/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 11/7/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/9/2023 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 11/9/2023 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/17/2023 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 11/17/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/17/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 11/28/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/28/2023 | Corrections Issued | OSVALDO PARAMO |
| Insulation | 11/30/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 12/6/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 12/6/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/11/2023 | Partial Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/5/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 1/5/2024 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 1/10/2024 | Partial Approval | OSVALDO PARAMO |
| Gas Test | 3/5/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 3/6/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/11/2024 | Approved | OSVALDO PARAMO |
| Final | 3/11/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/11/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 3/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 3/11/2024 | Approved | OSVALDO PARAMO |
| Final | 3/14/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 3/14/2024 | Approved | OSVALDO PARAMO |
| Final | 4/29/2024 | OK to Issue CofO | OSVALDO PARAMO |