8064 S ALTAVAN AVE 90045
Certificate Information: 8064 S ALTAVAN AVE 90045
- Application / Permit
- 22014-10000-05506
- Plan Check / Job No.
- B22LA22548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 13'-0" X 17'-9" AND 2'-6" x 30'-9" TO (E) SFD AND ENCLOSE (E) FRONT PORCH TO BE PART OF S.F.D. ADDING (N) COVERED PORCH AT FRONT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/18/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/18/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/21/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 2/17/2023 | MIROOSH KHACHATOORIAN |
| Issued | 2/21/2023 | APPLICANT |
| CofO in Progress | 6/11/2025 | DAVID FEILER |
| Permit Finaled | 6/12/2025 | RICHARD STEINBACH |
| CofO Issued | 6/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 12/12/2022 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | JENSON LEE |
| Sewer availability | Cleared | 1/3/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | JENSON LEE |
Contact Information
| Contractor | Precise Home Builders Inc; Lic. No.: 515469-B | , |
| Engineer | Mansuri,, Mehran; Lic. No.: NA78614 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/31/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 3/31/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | JESUS PINEDA |
| Insulation | 4/6/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 4/24/2023 | Approved | BOBBY KEY |
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 5/22/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 5/22/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/22/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 5/25/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 5/25/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 5/31/2023 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/2/2023 | Approved | BOBBY KEY |
| Green Building Rough | 6/2/2023 | Approved | BOBBY KEY |
| Insulation | 6/2/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 6/8/2023 | Approved | BOBBY KEY |
| Final | 6/8/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Approved | BOBBY KEY |
| Final | 7/21/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/21/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 7/21/2023 | Approved | BOBBY KEY |
| Deputy Wood Construction | 3/26/2024 | Conditional Approval | BOBBY KEY |
| Final | 6/11/2025 | OK to Issue CofO | DAVID FEILER |