798 W HOWARD ST 90292

Certificate Information: 798 W HOWARD ST 90292

Application / Permit
22014-10000-05492
Plan Check / Job No.
B22LA22503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan new NEW ADU WITH ROOF DECK OVER (E) 2-CAR GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/22/2024
Issuing Office
Current Status
CofO Issued on 1/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 MAHNAZ NOURHASHEMI
Corrections Issued 12/6/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 12/9/2022 GARO TELMI
Applicant returned to address corrections 10/31/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 12/8/2023 MAHNAZ NOURHASHEMI
Issued 2/22/2024 APPLICANT
CofO in Progress 1/29/2025 JESUS PINEDA
Permit Finaled 1/30/2025 RICHARD STEINBACH
CofO Issued 1/30/2025 RICHARD STEINBACH
Permit Finaled 1/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 1/9/2023 FREDDY GARCIA
Specific Plan Cleared 1/9/2023 FREDDY GARCIA
Address approval Cleared 1/19/2023 JENSON LEE
Low Impact Development Cleared 5/22/2023 MELINEH AGHAKHABIAN
Hydrant and Access approval Cleared 5/23/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 7/5/2023 DARIN LAM
Roof/Waste drainage to street Cleared 7/5/2023 DARIN LAM
Sewer availability Cleared 7/5/2023 DARIN LAM
Specific Plan Cleared 10/17/2023 CLAUDE GOODING
Specific Plan Cleared 10/17/2023 CLAUDE GOODING
ZA Case Cleared 10/17/2023 CLAUDE GOODING
ZA Case Cleared 10/17/2023 CLAUDE GOODING

Contact Information

Contractor Mid Construction Group; Lic. No.: 1030925-B       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401
Engineer Christiansen,, Scott; Lic. No.: NA37989       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/26/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 3/26/2024 Corrections Issued JESUS RODRIGUEZ
METHANE-Barrier 3/26/2024 Corrections Issued JESUS RODRIGUEZ
METHANE-Subgrade 3/26/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 4/2/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/5/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 5/17/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 5/17/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/17/2024 Approved JESUS RODRIGUEZ
Sewer 5/17/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 5/17/2024 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/20/2024 Corrections Issued JESUS RODRIGUEZ
Shower Pan 6/20/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/20/2024 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 6/26/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 7/25/2024 Approved JESUS RODRIGUEZ
Green Building Rough 7/25/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 7/25/2024 Approved JESUS RODRIGUEZ
Insulation 7/31/2024 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 7/31/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 8/5/2024 Not Ready for Inspection JESUS RODRIGUEZ
Insulation 8/5/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 8/7/2024 Approved HERBERT GIRON
ELECTRICAL-Final 10/29/2024 Approved JESUS PINEDA
Final 10/29/2024 Corrections Issued JESUS PINEDA
HVAC-Final 10/29/2024 Approved JESUS PINEDA
PLUMBING-Final 10/29/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Not Required JESUS PINEDA
Service/Power Release 10/29/2024 Not Required JESUS PINEDA
Smoke Detectors 10/29/2024 Approved JESUS PINEDA
ELECTRICAL-Final 1/29/2025 Approved JESUS PINEDA
Final 1/29/2025 OK to Issue CofO JESUS PINEDA
HVAC-Final 1/29/2025 Approved JESUS PINEDA
PLUMBING-Final 1/29/2025 Approved JESUS PINEDA
Service/Power Release 1/29/2025 Approved JESUS PINEDA