1855 W 38TH ST 90062
Certificate Information: 1855 W 38TH ST 90062
- Application / Permit
- 22014-10000-05487
- Plan Check / Job No.
- B22LA22489
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 24'-6" x 27'-0" IRREGULAR SHAPED ADDITION TO THE (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 11/21/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 12/12/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/12/2023 | SARKIS HARABEDIAN |
| Issued | 5/10/2023 | APPLICANT |
| CofO in Progress | 7/11/2024 | SABAS ALONSO |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | CINDY QI |
| Sewer availability | Cleared | 3/20/2023 | CINDY QI |
| Construction near power lines | Cleared | 4/8/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/8/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Visionary Design & Construction; Lic. No.: 1095931-B | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 6/23/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/7/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/22/2023 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 8/31/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 10/20/2023 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 10/20/2023 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 1/3/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 1/24/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 1/24/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 1/24/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 1/24/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 2/1/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/1/2024 | Approved | SABAS ALONSO |
| Insulation | 2/12/2024 | Corrections Issued | SABAS ALONSO |
| Insulation | 2/15/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/1/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 3/1/2024 | Partial Approval | JOSH MEISTER |
| Shower Pan | 3/1/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 4/11/2024 | Approved | JOSH MEISTER |
| Final | 6/18/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 6/18/2024 | Approved | SABAS ALONSO |
| Green Building Final | 6/18/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 6/18/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/18/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 6/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 6/25/2024 | Approved | SABAS ALONSO |
| Final | 6/25/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/25/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 6/25/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/25/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 6/25/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 6/25/2024 | Approved | SABAS ALONSO |
| Final | 7/10/2024 | OK to Issue CofO | SABAS ALONSO |