3355 1/2 W ATWATER AVE 90039
Certificate Information: 3355 1/2 W ATWATER AVE 90039
- Application / Permit
- 22014-10000-05486
- Plan Check / Job No.
- B22LA22484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE AND (N) ADDITION INTO (N) ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/11/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/14/2022 | FERNANDO FLORES |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 4/17/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
| CofO Issued | 4/18/2024 | DEROLD HAUFF |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/16/2022 | WALLIE JONG |
| Sewer availability | Cleared | 11/16/2022 | WALLIE JONG |
Contact Information
| Engineer | Peek,, Justen N; Lic. No.: C76751 | 702 RIO GRANDE CT BRENTWOOD, CA 94513 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/5/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/5/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/10/2023 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/14/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/21/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/28/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/3/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/3/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/3/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/10/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 8/10/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/10/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/25/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/25/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/31/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/14/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 11/14/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/14/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/28/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/28/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 11/28/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/8/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/22/2023 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 12/22/2023 | Approved | CHARLES BOGHOSKHAN |
| Final | 4/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/10/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 4/10/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/10/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 4/15/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/15/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Final | 4/16/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/16/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV No Gas | HAMIK HARTOUNIAN |