3355 1/2 W ATWATER AVE 90039

Certificate Information: 3355 1/2 W ATWATER AVE 90039

Application / Permit
22014-10000-05486
Plan Check / Job No.
B22LA22484
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE AND (N) ADDITION INTO (N) ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 1/17/2023
Issuing Office
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 LUISANGEL VALENZUELA
Corrections Issued 11/11/2022 LUISANGEL VALENZUELA
Plan Check Approved 12/14/2022 FERNANDO FLORES
Issued 1/17/2023 APPLICANT
CofO in Progress 4/17/2024 HAMIK HARTOUNIAN
Permit Finaled 4/18/2024 DEROLD HAUFF
CofO Issued 4/18/2024 DEROLD HAUFF
Permit Finaled 4/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/16/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/16/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 11/16/2022 WALLIE JONG
Sewer availability Cleared 11/16/2022 WALLIE JONG

Contact Information

Engineer Peek,, Justen N; Lic. No.: C76751 702 RIO GRANDE CT      BRENTWOOD, CA 94513

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2023 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/5/2023 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 4/5/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/10/2023 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/14/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 4/14/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/21/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/28/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 7/28/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 7/28/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/3/2023 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 8/3/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 8/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 8/3/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/10/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 8/10/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 8/10/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/25/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/25/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/31/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/14/2023 Corrections Issued HAMIK HARTOUNIAN
Insulation 11/14/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/14/2023 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/28/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/28/2023 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 11/28/2023 Approved HAMIK HARTOUNIAN
Insulation 12/8/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/22/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 12/22/2023 Approved CHARLES BOGHOSKHAN
Final 4/10/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/10/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 4/10/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 4/10/2024 Approved HAMIK HARTOUNIAN
Final 4/15/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/15/2024 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV No Gas HAMIK HARTOUNIAN
Final 4/16/2024 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/16/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV No Gas HAMIK HARTOUNIAN