7015 S VAN NESS AVE 90047

Certificate Information: 7015 S VAN NESS AVE 90047

Application / Permit
22014-10000-05485
Plan Check / Job No.
B22LA22483
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
ADDITION OF TWO (2) ADA ACCESSIBLE TOILETS TO AN EXISTING CHURCH.
Permit Issued
Issued on 4/14/2025
Issuing Office
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 HERNAN ARREOLA
Corrections Issued 11/21/2022 HERNAN ARREOLA
Quality Review Completed 11/29/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 5/12/2023 HERNAN ARREOLA
Issued 4/14/2025 APPLICANT
CofO in Progress 11/21/2025 ALFREDO LOPEZ
Permit Finaled 11/21/2025 ERNESTO CORRAL
CofO Issued 11/21/2025 ERNESTO CORRAL
Permit Finaled 11/21/2025 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 12/1/2022 RYAN LY
Roof/Waste drainage to street Cleared 12/12/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/21/2022 CINDY QI
Green Code Cleared 4/18/2023 DONALD CRICHLOW
DAS Clearance Cleared 5/1/2023 Rosendo Medina

Contact Information

Architect Kerr,, Robert E; Lic. No.: NA28038       ,
Contractor Vancrest Construction Corp; Lic. No.: 393800-B       ,
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/5/2025 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Conditional Approval DARRYL ARNOLD
Green Building Rough 5/21/2025 Conditional Approval DARRYL ARNOLD
Insulation 5/21/2025 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 5/21/2025 Not Ready for Inspection DARRYL ARNOLD
Green Building Rough 5/29/2025 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 6/4/2025 Partial Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Approved ALFREDO LOPEZ
Green Building Rough 6/4/2025 Approved ALFREDO LOPEZ
Insulation 6/4/2025 Approved ALFREDO LOPEZ
Wood Frame 6/4/2025 Approved ALFREDO LOPEZ
Drywall Nailing 6/5/2025 Approved DARRYL ARNOLD
Interior/Exterior Lathing 6/9/2025 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/7/2025 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 7/7/2025 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 7/7/2025 Not Ready for Inspection ALFREDO LOPEZ
Final 7/14/2025 Partial Inspection ALFREDO LOPEZ
Final 11/21/2025 OK to Issue CofO ALFREDO LOPEZ
Footing/Foundation/Slab 11/21/2025 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 11/21/2025 Approved ALFREDO LOPEZ