7015 S VAN NESS AVE 90047
Certificate Information: 7015 S VAN NESS AVE 90047
- Application / Permit
- 22014-10000-05485
- Plan Check / Job No.
- B22LA22483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- ADDITION OF TWO (2) ADA ACCESSIBLE TOILETS TO AN EXISTING CHURCH.
- Permit Issued
- Issued on 4/14/2025
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | HERNAN ARREOLA |
| Corrections Issued | 11/21/2022 | HERNAN ARREOLA |
| Quality Review Completed | 11/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/12/2023 | HERNAN ARREOLA |
| Issued | 4/14/2025 | APPLICANT |
| CofO in Progress | 11/21/2025 | ALFREDO LOPEZ |
| Permit Finaled | 11/21/2025 | ERNESTO CORRAL |
| CofO Issued | 11/21/2025 | ERNESTO CORRAL |
| Permit Finaled | 11/21/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/1/2022 | RYAN LY |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | CINDY QI |
| Green Code | Cleared | 4/18/2023 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 5/1/2023 | Rosendo Medina |
Contact Information
| Architect | Kerr,, Robert E; Lic. No.: NA28038 | , |
| Contractor | Vancrest Construction Corp; Lic. No.: 393800-B | , |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Conditional Approval | DARRYL ARNOLD |
| Green Building Rough | 5/21/2025 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 5/21/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 5/21/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Rough | 5/29/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 6/4/2025 | Partial Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | ALFREDO LOPEZ |
| Green Building Rough | 6/4/2025 | Approved | ALFREDO LOPEZ |
| Insulation | 6/4/2025 | Approved | ALFREDO LOPEZ |
| Wood Frame | 6/4/2025 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 6/5/2025 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 6/9/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/7/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 7/7/2025 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 7/7/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 7/14/2025 | Partial Inspection | ALFREDO LOPEZ |
| Final | 11/21/2025 | OK to Issue CofO | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 11/21/2025 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 11/21/2025 | Approved | ALFREDO LOPEZ |