2700 S RIMPAU BLVD 90016
Certificate Information: 2700 S RIMPAU BLVD 90016
- Application / Permit
- 22014-10000-05479
- Plan Check / Job No.
- B22LA22461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Current Status
- CofO in Progress on 12/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | DANIEL YIP |
| Corrections Issued | 11/11/2022 | DANIEL YIP |
| Plan Check Approved | 12/12/2022 | JOE VO |
| Issued | 12/13/2022 | APPLICANT |
| CofO in Progress | 12/5/2023 | WILLIAM MICHALAK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/5/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/6/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/13/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 4/24/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 5/2/2023 | Corrections Issued | CALEB MEISTER |
| Insulation | 6/13/2023 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 7/18/2023 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 7/18/2023 | Approved | WILLIAM MICHALAK |
| Insulation | 8/4/2023 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 8/21/2023 | Partial Approval | WILLIAM MICHALAK |
| Green Building Rough | 8/21/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 8/21/2023 | Corrections Issued | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 8/25/2023 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 9/13/2023 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 10/26/2023 | Approved | WILLIAM MICHALAK |
| Final | 10/26/2023 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 10/26/2023 | Approved | WILLIAM MICHALAK |
| Green Building Final | 10/26/2023 | Approved | WILLIAM MICHALAK |
| Green Building Rough | 10/26/2023 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 10/26/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 11/16/2023 | Corrections Issued | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 11/16/2023 | Approved | WILLIAM MICHALAK |
| Final | 12/1/2023 | OK to Issue CofO | WILLIAM MICHALAK |