939 W 61ST ST 90044

Certificate Information: 939 W 61ST ST 90044

Application / Permit
22014-10000-05471
Plan Check / Job No.
B22LA22450
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED GROUND FLOOR AND 2ND STORY ADDITION TO (E) 1 STORY SFD, BUILDING SHALL BE EQUIPPED WITH AUTOMATIC SPRINKLERS SYSTEM PER NFPA-13D.
Permit Issued
Issued on 3/1/2024
Issuing Office
Metro
Current Status
Issued on 3/1/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 ARMEN JIVALAGIAN
Corrections Issued 12/6/2022 ARMEN JIVALAGIAN
Quality Review Completed 12/8/2022 PETER KIM
Building Plans Picked Up 12/19/2022 APPLICANT
Applicant returned to address corrections 7/10/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/25/2024 ARMEN JIVALAGIAN
Plan Check Approved 2/15/2024 ARMEN JIVALAGIAN
Issued 3/1/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/3/2023 AMAAN MALIK
Frnt yard landscape/Water mgmt Cleared 3/23/2023 DANIEL CORONADO
Low Impact Development Cleared 6/6/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/9/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/25/2024 DAVID VO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241
Engineer Vesga,, Luis Fernando; Lic. No.: C68782 10 TUMBLEWEED ST      TRABUCO CANYON, CA 92679

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/24/2024 No Access for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/2/2024 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 7/2/2024 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 7/5/2024 Approved CRAIG DAVIS
Footing/Foundation/Slab 7/5/2024 Approved CRAIG DAVIS
Wood Frame 9/4/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 11/22/2024 Conditional Approval JOSE MACIAS
ELECTRICAL-Rough 11/22/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Conditional Approval JOSE MACIAS
Green Building Rough 11/22/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 11/22/2024 Approved JOSE MACIAS
Shower Pan 11/22/2024 Approved JOSE MACIAS
Insulation 12/23/2024 Corrections Issued BARRY HACHE
Verify Sprinkler Sign Off 12/23/2024 Approved BARRY HACHE
HVAC-Rough 12/27/2024 Approved BARRY HACHE
Insulation 12/27/2024 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 1/3/2025 Approved BARRY HACHE
Green Building Rough 1/3/2025 Approved BARRY HACHE
Insulation 1/3/2025 Approved BARRY HACHE
PLUMBING-Rough 1/3/2025 Approved BARRY HACHE
Drywall Nailing 1/24/2025 Approved BARRY HACHE
Interior/Exterior Lathing 1/24/2025 Approved BARRY HACHE