211 W 94TH ST 90003
Certificate Information: 211 W 94TH ST 90003
- Application / Permit
- 22014-10000-05462
- Plan Check / Job No.
- B22LA22436
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached 2-car garage to ADU and addition to ADU per Ordinance. Addition to existing 1-story SFD at rear of lot
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Current Status
- CofO Corrected on 2/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | VICTOR CHEN |
| Corrections Issued | 11/17/2022 | VICTOR CHEN |
| Building Plans Picked Up | 11/30/2022 | APPLICANT |
| Plan Check Approved | 2/28/2024 | DANIEL SANJUAN |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 2/14/2025 | JOSEPH MCGARRY |
| CofO Issued-Status Void | 2/14/2025 | ANSON MAGLASANG |
| Permit Finaled-Status Void | 2/14/2025 | ANSON MAGLASANG |
| Re-Activate Permit | 2/4/2026 | ANSON MAGLASANG |
| Permit Finaled | 2/4/2026 | ANSON MAGLASANG |
| CofO Corrected | 2/4/2026 | ANSON MAGLASANG |
| Permit Finaled | 2/4/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2023 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 2/21/2024 | LUIS CRUZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/23/2024 | WALLIE JONG |
| Sewer availability | Cleared | 2/23/2024 | WALLIE JONG |
Contact Information
| Contractor | Alfredo'S Construction; Lic. No.: 1016778-B | 1743 W 50TH STREET LOS ANGELES, CA 90062 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/31/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 6/4/2024 | Partial Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Approved | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 8/13/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 8/19/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/19/2024 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/19/2024 | Corrections Issued | JOSEPH MCGARRY |
| MERV13>=Rough | 8/19/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/19/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/28/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 8/28/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 8/28/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 8/28/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 8/28/2024 | Partial Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 9/5/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 9/5/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 9/10/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 9/10/2024 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Rough | 9/13/2024 | Approved | BARRY HACHE |
| Insulation | 9/13/2024 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 9/13/2024 | Approved | BARRY HACHE |
| Drywall Nailing | 9/25/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 9/25/2024 | Approved | BEN MOLSTAD |
| Sewer | 9/25/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 9/27/2024 | Approved | BEN MOLSTAD |
| Sewer | 9/27/2024 | Approved | BEN MOLSTAD |
| Final | 2/13/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 2/13/2025 | Approved | JOSEPH MCGARRY |
| MERV13>=Final | 2/13/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/13/2025 | Approved | JOSEPH MCGARRY |