1524 N ORANGE GROVE AVE 90046

Certificate Information: 1524 N ORANGE GROVE AVE 90046

Application / Permit
22014-10000-05450
Plan Check / Job No.
B22LA22373
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ground floor addition, pergola, outdoor BBQ and sink to (e) 2-story SFD
Permit Issued
Issued on 3/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 KELVIN CHUONG
Corrections Issued 12/1/2022 KELVIN CHUONG
Quality Review Completed 12/2/2022 KEN GILL
Building Plans Picked Up 12/13/2022 APPLICANT
Applicant returned to address corrections 3/21/2023 KELVIN CHUONG
Plan Check Approved 3/29/2023 KELVIN CHUONG
Issued 3/30/2023 APPLICANT
CofO in Progress 6/13/2024 STUART CHAPMAN
CofO Issued 6/14/2024 DEROLD HAUFF
Permit Finaled 6/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/17/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/3/2023 AMAAN MALIK
HPOZ Cleared 1/30/2023 AMANDA KAINER
Low Impact Development Cleared 2/15/2023 ERNEST TSE

Contact Information

Contractor Resourceful Construction Inc; Lic. No.: 1003215-B 1958 AVON STREET      LOS ANGELES, CA 90026
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/18/2023 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/18/2023 Approved RAUL BARAJAS
PLUMBING-Rough 4/18/2023 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 5/3/2023 Approved STUART CHAPMAN
PLUMBING-Rough 5/3/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/19/2023 Approved STUART CHAPMAN
HVAC-Rough 5/19/2023 Approved STUART CHAPMAN
Insulation 5/25/2023 Approved RAUL BARAJAS
Shower Pan 5/31/2023 Approved STUART CHAPMAN
Drywall Nailing 6/6/2023 Approved RAUL BARAJAS
Green Building Rough 6/6/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 6/13/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 9/18/2023 Not Ready for Inspection STUART CHAPMAN
Final 9/18/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 9/18/2023 Approved STUART CHAPMAN
Green Building Final 9/18/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 9/18/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/21/2023 Approved STUART CHAPMAN
Final 9/21/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 3/28/2024 Approved STUART CHAPMAN
Final 3/28/2024 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 3/28/2024 Approved STUART CHAPMAN
PLUMBING-Final 3/28/2024 Approved STUART CHAPMAN
Final 6/13/2024 OK to Issue CofO STUART CHAPMAN