1135 W 41ST ST 90037
Certificate Information: 1135 W 41ST ST 90037
- Application / Permit
- 22014-10000-05445
- Plan Check / Job No.
- B22LA22350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 360sqft Garage Conversion and Irregular addtion 322sqft to make 682sqft ADU per state law "COMPLY WITH DEPARTMENT ORDER effective date 10/06/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".CEIS Case Number is 969162.
- Permit Issued
- Issued on 3/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | ZAW HAN |
| Corrections Issued | 11/15/2022 | ZAW HAN |
| Building Plans Picked Up | 12/6/2022 | APPLICANT |
| Plan Check Approved | 5/4/2023 | ZAW HAN |
| Plan Check Approved | 5/4/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 6/11/2023 | JOSEPH RAFOLS |
| No Progress | 6/13/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 2/27/2024 | KHUONG TRUONG |
| Issued | 3/29/2024 | APPLICANT |
| CofO in Progress | 1/27/2025 | DANIEL GUEVARA |
| Permit Finaled | 2/6/2025 | CLAUDIO MORENO |
| CofO Issued | 2/6/2025 | CLAUDIO MORENO |
| Permit Finaled | 2/6/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/31/2022 | ABEL CASILLAS |
| Address approval | Cleared | 1/9/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/9/2023 | ABEL CASILLAS |
| Low Impact Development (LID) | Cleared | 12/5/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 12/7/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Baron Construction & Design Llc; Lic. No.: 917339-B | 7608 OAK PARK AVE VAN NUYS, CA 91406 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/22/2024 | Partial Approval | DANIEL GONZALEZ |
| Sewer | 4/22/2024 | Partial Approval | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Approved | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 5/1/2024 | Approved | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Corrections Issued | DANIEL GUEVARA |
| Deputy Drilled-In Anchors | 6/3/2024 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 7/15/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| ELECTRICAL-Rough | 7/15/2024 | Approved | DANIEL GUEVARA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Approved | DANIEL GUEVARA |
| HVAC-Rough | 7/15/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| PLUMBING-Rough | 7/15/2024 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | DANIEL GONZALEZ |
| Green Building Rough | 7/23/2024 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 7/23/2024 | Partial Approval | DANIEL GONZALEZ |
| Shower Pan | 7/23/2024 | Approved | DANIEL GONZALEZ |
| HVAC-Rough | 7/31/2024 | Corrections Issued | ENRIQUE PREZA |
| Insulation | 7/31/2024 | Approved | ENRIQUE PREZA |
| Drywall Nailing | 8/7/2024 | Approved | DANIEL GONZALEZ |
| Pre-Inspection | 8/7/2024 | Partial Approval | DANIEL GONZALEZ |
| ELECTRICAL-Final | 10/30/2024 | Approved | DANIEL GONZALEZ |
| Final | 10/30/2024 | Corrections Issued | DANIEL GONZALEZ |
| Green Building Final | 10/30/2024 | Approved | DANIEL GONZALEZ |
| HVAC-Final | 10/30/2024 | Approved | DANIEL GONZALEZ |
| PLUMBING-Final | 10/30/2024 | Approved | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 10/30/2024 | SGSOV Approved | DANIEL GONZALEZ |
| Smoke Detectors | 10/30/2024 | Approved | DANIEL GONZALEZ |
| Final | 1/22/2025 | OK to Issue CofO | DANIEL GUEVARA |