8424 S FORDHAM ROAD 90045

Certificate Information: 8424 S FORDHAM ROAD 90045

Application / Permit
22014-10000-05440
Plan Check / Job No.
B22LA22314
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Attached bathroom addition (117 SF) to rear of (E) 1-story SFD per engineer's calcs
Permit Issued
Issued on 1/20/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 FERNANDO FLORES
Corrections Issued 11/3/2022 DANIEL SMILEY
Applicant returned to address corrections 1/3/2023 JOHNPAUL ISIP
Applicant returned to address corrections 1/13/2023 JOHNPAUL ISIP
Plan Check Approved 1/20/2023 JOHNPAUL ISIP
Issued 1/20/2023 APPLICANT
CofO in Progress 1/9/2024 BOBBY KEY
Permit Finaled 1/12/2024 DANIEL ORRANTE
CofO Issued 1/12/2024 DANIEL ORRANTE
Permit Finaled 1/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 1/11/2023 EDUARDO HERMOSO
Roof/Waste drainage to street Cleared 1/11/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 1/17/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/26/2023 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 2/14/2023 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 3/29/2023 Approved BOBBY KEY
Wood Frame 3/29/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 3/31/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Partial Approval BOBBY KEY
Interior/Exterior Lathing 5/24/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Approved BOBBY KEY
Green Building Rough 6/12/2023 Corrections Issued BOBBY KEY
Rough-Elec/Plmb/HVAC 6/12/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 6/15/2023 Approved BOBBY KEY
Green Building Rough 6/15/2023 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 6/15/2023 Approved BOBBY KEY
Drywall Nailing 6/20/2023 Approved BOBBY KEY
ELECTRICAL-Final 9/20/2023 Approved BOBBY KEY
Final 9/20/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved BOBBY KEY
Shower Pan 9/20/2023 Approved BOBBY KEY
Interior/Exterior Lathing 10/3/2023 Approved TEMISTOCLES CAAL
Final 1/9/2024 OK to Issue CofO BOBBY KEY
Green Building Final 1/9/2024 Approved BOBBY KEY
HVAC-Final 1/9/2024 Approved BOBBY KEY
PLUMBING-Final 1/9/2024 Approved BOBBY KEY
Smoke Detectors 1/9/2024 Approved BOBBY KEY