14145 W WEDDINGTON ST 91401
Certificate Information: 14145 W WEDDINGTON ST 91401
- Application / Permit
- 22014-10000-05439
- Plan Check / Job No.
- B22LA22301
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan one story addition to existing single family. COMPLY WITH DEPARTMENT ORDER effective date 02/15/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 12/14/2022
- Issuing Office
- Current Status
- CofO Issued on 4/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | AMY GUEVARRA |
| Corrections Issued | 11/10/2022 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/29/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 12/5/2022 | AMY GUEVARRA |
| Plan Check Approved | 12/7/2022 | AMY GUEVARRA |
| Issued | 12/14/2022 | APPLICANT |
| CofO in Progress | 10/6/2025 | PTOLEMY HILL |
| Permit Finaled | 4/1/2026 | DANIEL SANCHEZ |
| CofO Issued | 4/1/2026 | DANIEL SANCHEZ |
| Permit Finaled | 4/1/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/14/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/3/2023 | No Access for Inspection | PATRICK LIEBREGT |
| Green Building Rough | 2/3/2023 | No Access for Inspection | PATRICK LIEBREGT |
| Wood Frame | 2/15/2023 | Corrections Issued | PATRICK LIEBREGT |
| Interior/Exterior Lathing | 2/27/2023 | Approved | PATRICK LIEBREGT |
| Insulation | 3/9/2023 | Partial Approval | PATRICK LIEBREGT |
| Drywall Nailing | 3/13/2023 | Approved | PATRICK LIEBREGT |
| Green Building Rough | 3/13/2023 | Approved | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 6/30/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Final | 6/30/2025 | Corrections Issued | JONATHAN FRANCHINI |
| Footing/Foundation/Slab | 6/30/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Green Building Final | 6/30/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | JONATHAN FRANCHINI |
| Smoke Detectors | 6/30/2025 | Approved | JONATHAN FRANCHINI |
| BUILDING-Rough-Frame | 7/14/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Final | 7/14/2025 | Corrections Issued | JONATHAN FRANCHINI |
| Footing/Foundation/Slab | 7/14/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Green Building Final | 7/14/2025 | Partial Approval | JONATHAN FRANCHINI |
| Deputy Drilled-In Anchors | 7/25/2025 | Approved | JONATHAN FRANCHINI |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | PTOLEMY HILL |
| Final | 10/3/2025 | OK to Issue CofO | PTOLEMY HILL |
| Footing/Foundation/Slab | 10/3/2025 | Approved | PTOLEMY HILL |
| Green Building Final | 10/3/2025 | Approved | PTOLEMY HILL |