Work Description
eplan one story addition to existing single family. COMPLY WITH DEPARTMENT ORDER effective date 02/15/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 12/14/2022
Issuing Office
Current Status
CofO Issued on 4/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 AMY GUEVARRA
Corrections Issued 11/10/2022 AMY GUEVARRA
Applicant returned to address corrections 11/29/2022 ALFREDO JARA
Applicant returned to address corrections 12/5/2022 AMY GUEVARRA
Plan Check Approved 12/7/2022 AMY GUEVARRA
Issued 12/14/2022 APPLICANT
CofO in Progress 10/6/2025 PTOLEMY HILL
Permit Finaled 4/1/2026 DANIEL SANCHEZ
CofO Issued 4/1/2026 DANIEL SANCHEZ
Permit Finaled 4/1/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/14/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/15/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/3/2023 No Access for Inspection PATRICK LIEBREGT
Green Building Rough 2/3/2023 No Access for Inspection PATRICK LIEBREGT
Wood Frame 2/15/2023 Corrections Issued PATRICK LIEBREGT
Interior/Exterior Lathing 2/27/2023 Approved PATRICK LIEBREGT
Insulation 3/9/2023 Partial Approval PATRICK LIEBREGT
Drywall Nailing 3/13/2023 Approved PATRICK LIEBREGT
Green Building Rough 3/13/2023 Approved PATRICK LIEBREGT
BUILDING-Rough-Frame 6/30/2025 Not Ready for Inspection JONATHAN FRANCHINI
Final 6/30/2025 Corrections Issued JONATHAN FRANCHINI
Footing/Foundation/Slab 6/30/2025 Not Ready for Inspection JONATHAN FRANCHINI
Green Building Final 6/30/2025 Not Ready for Inspection JONATHAN FRANCHINI
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Approved JONATHAN FRANCHINI
Smoke Detectors 6/30/2025 Approved JONATHAN FRANCHINI
BUILDING-Rough-Frame 7/14/2025 Not Ready for Inspection JONATHAN FRANCHINI
Final 7/14/2025 Corrections Issued JONATHAN FRANCHINI
Footing/Foundation/Slab 7/14/2025 Not Ready for Inspection JONATHAN FRANCHINI
Green Building Final 7/14/2025 Partial Approval JONATHAN FRANCHINI
Deputy Drilled-In Anchors 7/25/2025 Approved JONATHAN FRANCHINI
BUILDING-Rough-Frame 10/3/2025 Approved PTOLEMY HILL
Final 10/3/2025 OK to Issue CofO PTOLEMY HILL
Footing/Foundation/Slab 10/3/2025 Approved PTOLEMY HILL
Green Building Final 10/3/2025 Approved PTOLEMY HILL