**ePlan** Interior remodel and addition of on second floor to existing 2-story Single Family Dwelling.. **The project is exempt from BHO since the total cumulative Residential Floor Area of all additions is less than 500 sf since 8/1/2010, and the addition complies with BHO height, setback and grading limitations.**
Permit Issued
Issued on 3/31/2023
Issuing Office
Current Status
Issued on 3/31/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 JOHNNY WU
Corrections Issued 12/2/2022 JOHNNY WU
Quality Review Completed 12/7/2022 RODOLFO ARIAS
Applicant returned to address corrections 3/21/2023 JOHNNY WU
Plan Check Approved 3/21/2023 JOHNNY WU
Issued 3/31/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 12/5/2022 JAZMIN ROQUE
Roof/Waste drainage to street Cleared 12/12/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/13/2022 AMAAN MALIK
Grading Pre-Inspection Cleared 1/17/2023 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: NA37989       ,
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2023 Partial Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/8/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 5/8/2023 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/10/2023 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 5/10/2023 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/18/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 11/21/2023 Approved BRIAN SULLIVAN
PLUMBING-Rough 11/21/2023 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 11/27/2023 Approved BRIAN SULLIVAN
Insulation 1/29/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 1/29/2024 Partial Approval BRIAN SULLIVAN
Drywall Nailing 2/20/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 4/17/2024 Partial Inspection RAUL BARAJAS
Shower Pan 4/17/2024 Approved RAUL BARAJAS
Special/Order Compliance 9/19/2024 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 9/23/2024 Partial Inspection BRIAN SULLIVAN
Special/Order Compliance 11/5/2024 Order to Comply Issued BRIAN SULLIVAN
Interior/Exterior Lathing 12/5/2024 Conditional Approval BRIAN SULLIVAN
Special/Order Compliance 12/5/2024 Partial Inspection BRIAN SULLIVAN
Special/Order Compliance 3/26/2025 Partial Inspection ALEX COLIN
ELECTRICAL-Final 8/6/2025 Corrections Issued SCOTT FINNILA
Service/Power Release 8/6/2025 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/6/2026 Approved SCOTT FINNILA
ELECTRICAL-Final 3/6/2026 Approved SCOTT FINNILA
Final 3/6/2026 Not Ready for Inspection SCOTT FINNILA
HVAC-Final 3/6/2026 Corrections Issued SCOTT FINNILA
PLUMBING-Final 3/6/2026 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved SCOTT FINNILA
Smoke Detectors 3/6/2026 Approved SCOTT FINNILA
Final 3/26/2026 Partial Inspection BRIAN SULLIVAN
HVAC-Final 3/26/2026 Approved BRIAN SULLIVAN
PLUMBING-Final 3/26/2026 Approved BRIAN SULLIVAN