3515 S BARRINGTON AVE 90066
Certificate Information: 3515 S BARRINGTON AVE 90066
- Application / Permit
- 22014-10000-05435
- Plan Check / Job No.
- B22LA22281
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major remodel to 1st story of (e) SFD and addition of 2nd floor. 1 exisiting wall to remain
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | JAD BASMA |
| Corrections Issued | 11/10/2022 | JAD BASMA |
| Quality Review Completed | 11/16/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 4/14/2023 | JAD BASMA |
| Issued | 4/17/2023 | APPLICANT |
| CofO in Progress | 5/14/2024 | JESUS PINEDA |
| Permit Finaled | 5/16/2024 | DANIEL ORRANTE |
| CofO Issued | 5/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/27/2023 | ROGELIO CORTES |
| Permit | Cleared | 2/27/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 3/8/2023 | JENSON LEE |
| Sewer availability | Cleared | 3/8/2023 | JENSON LEE |
| Specific Plan | Cleared | 3/8/2023 | ROBERT SANCHEZ |
| Trees in Parkway | Cleared | 3/30/2023 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 4/14/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 4/14/2023 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/9/2023 | No Access for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 5/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Pre-Inspection | 5/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 5/25/2023 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/26/2023 | Approved | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 6/2/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 6/20/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Partial Approval | JEREMY TODD |
| Green Building Rough | 7/3/2023 | Not Ready for Inspection | JEREMY TODD |
| PLUMBING-Rough | 8/1/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 8/2/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 8/2/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 8/7/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 8/10/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 8/11/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/22/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 8/22/2023 | Corrections Issued | JESUS PINEDA |
| Insulation | 8/22/2023 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 8/22/2023 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 8/22/2023 | Partial Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 8/23/2023 | Partial Approval | JESUS PINEDA |
| Shower Pan | 8/23/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/28/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 8/28/2023 | Approved | JESUS PINEDA |
| Insulation | 8/28/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/28/2023 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 8/31/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/31/2023 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 8/31/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Drywall Nailing | 9/6/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 3/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 3/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 3/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 3/8/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/12/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/12/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 4/19/2024 | Approved | JESUS PINEDA |
| Final | 4/19/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/19/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 4/19/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 4/19/2024 | Approved | JESUS PINEDA |
| Final | 5/10/2024 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 5/10/2024 | Approved | JESUS PINEDA |