5236 E BUCHANAN ST 90042

Certificate Information: 5236 E BUCHANAN ST 90042

Application / Permit
22014-10000-05424
Plan Check / Job No.
B22LA22230
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addtion at rear of exiting one story single family dewlling per WFPP. Dwelling to be fully sprinklered. "Comply with Department Order effective date03/21/2022. CEIS Case Number is 950855. Permit to expire 30 days from issuance date."
Permit Issued
Issued on 3/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 ZAW HAN
Corrections Issued 11/15/2022 ZAW HAN
Building Plans Picked Up 11/18/2022 APPLICANT
Plan Check Approved 2/21/2023 RICARDO RAMIREZ
Issued 3/28/2023 APPLICANT
CofO in Progress 5/14/2024 GABRIEL HERRERA
CofO Issued 5/15/2024 SHAWN ESHBACH
Permit Finaled 5/15/2024 SHAWN ESHBACH

Permit Application Clearance Information

Sewer availability Cleared 1/17/2023 AMAAN MALIK
Grading Pre-Inspection Cleared 1/19/2023 ALEXANDER HELFER
Hydrant and Access approval Cleared 2/7/2023 GILBERT URREA
Low Impact Development Cleared 2/15/2023 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 2/17/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 2/17/2023 JEANIE LAM
GPI Written Notices Cleared 2/21/2023 ZAW HAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EDMUND LUM, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
LUCIANO GAUNA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
JAIME RIOS, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
ANDEY CHAPARRO, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
RYAN BARNES, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
PATRICK LIEBREGT, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GLEN RAND, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
SHAWN ESHBACH, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GABRIEL HERRERA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2023 Corrections Issued GABRIEL HERRERA
Excavation/Setback/Form/Re-Bar 5/17/2023 Approved GABRIEL HERRERA
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Approved GABRIEL HERRERA
BUILDING-Rough-Frame 8/4/2023 Corrections Issued GABRIEL HERRERA
ELECTRICAL-Rough 8/4/2023 Corrections Issued GABRIEL HERRERA
Green Building Rough 8/4/2023 Not Ready for Inspection GABRIEL HERRERA
HVAC-Rough 8/4/2023 Approved GABRIEL HERRERA
MERV13>=Rough 8/4/2023 Approved GABRIEL HERRERA
PLUMBING-Rough 8/4/2023 Approved GABRIEL HERRERA
Interior/Exterior Lathing 8/15/2023 Approved GABRIEL HERRERA
BUILDING-Rough-Frame 9/13/2023 Approved GABRIEL HERRERA
ELECTRICAL-Rough 9/13/2023 Approved GABRIEL HERRERA
Green Building Rough 9/13/2023 Approved GABRIEL HERRERA
Insulation 9/13/2023 Approved GABRIEL HERRERA
Drywall Nailing 9/28/2023 Approved GABRIEL HERRERA
Service/Power Release 10/5/2023 Approved PATRICK LIEBREGT
Final 1/19/2024 Corrections Issued GABRIEL HERRERA
Footing/Foundation/Slab 1/19/2024 Approved GABRIEL HERRERA
Green Building Final 1/19/2024 Approved GABRIEL HERRERA
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Approved GABRIEL HERRERA
Smoke Detectors 1/19/2024 Approved GABRIEL HERRERA
Final 1/24/2024 Conditional Approval GABRIEL HERRERA
Final 5/14/2024 OK to Issue CofO GABRIEL HERRERA