8343 W RIDPATH DR 90046
Certificate Information: 8343 W RIDPATH DR 90046
- Application / Permit
- 22014-10000-05397
- Plan Check / Job No.
- B22LA22128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- Remove demising wall between kitchen and living room, and create 3rd bedroom, remove (E) front porch and remodel (E) coverred entrance no sqft added
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/19/2023
Permit Application Status History
| Submitted | 11/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2022 | MINA HABILI |
| Corrections Issued | 11/8/2022 | MINA HABILI |
| Applicant returned to address corrections | 11/22/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 12/14/2022 | KHUONG TRUONG |
| No Progress | 12/14/2022 | KHUONG TRUONG |
| Plan Check Approved | 12/14/2022 | KHUONG TRUONG |
| Issued | 12/16/2022 | APPLICANT |
| Permit Finaled | 12/19/2023 | RAUL BARAJAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/22/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 11/23/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Partial Inspection | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 5/4/2023 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/9/2023 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/22/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/21/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 7/21/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 7/21/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/11/2023 | Approved | RAUL BARAJAS |
| Shower Pan | 8/11/2023 | Approved | RAUL BARAJAS |
| Insulation | 8/16/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/16/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 8/25/2023 | Approved | RAUL BARAJAS |
| Final | 12/19/2023 | Permit Finaled | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/19/2023 | Approved | RAUL BARAJAS |