921 S 3RD AVE 90019
Certificate Information: 921 S 3RD AVE 90019
- Application / Permit
- 22014-10000-05396
- Plan Check / Job No.
- B22LA22126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU AND ADDITION TO THE ADU PER LAMC
- Permit Issued
- Issued on 2/2/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | WEIJIAN HUANG |
| Corrections Issued | 11/15/2022 | WEIJIAN HUANG |
| Building Plans Picked Up | 11/17/2022 | APPLICANT |
| Plan Check Approved | 1/11/2023 | JOSEPH RAFOLS |
| Issued | 2/2/2023 | APPLICANT |
| CofO in Progress | 2/1/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/6/2022 | TINA MIRANDA |
| Address approval | Cleared | 12/8/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/8/2022 | CINDY QI |
| Sewer availability | Cleared | 12/8/2022 | CINDY QI |
| HPOZ | Cleared | 1/4/2023 | AMANDA KAINER |
Contact Information
| Contractor | Soumekh Michael N; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 4/4/2023 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 4/4/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/13/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/19/2023 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/8/2023 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/2/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 8/2/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/2/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/2/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 8/2/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/4/2023 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/14/2023 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/14/2023 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 8/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 8/18/2023 | Conditional Approval | JEFFREY MEAD |
| Drywall Nailing | 8/25/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/25/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 1/26/2024 | Approved | JEFFREY MEAD |
| Final | 1/26/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 1/26/2024 | Approved | JEFFREY MEAD |
| HVAC-Final | 1/26/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 1/26/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 1/26/2024 | Approved | JEFFREY MEAD |
| Final | 1/31/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |