130 S ALVARADO ST 90057

Certificate Information: 130 S ALVARADO ST 90057

Application / Permit
22014-10000-05394
Plan Check / Job No.
B22LA22124
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Medical Clinic
Work Description
ePLAN- 1. CHANGE USE & TENANT IMPROVEMENT: PROPOSED CHANGE OF USE FROM OFFICE TO PRIMARY MEDICAL CARE CLINIC INCLUDING AN ADULT DAY CARE CENTER, A MEDICAL CLINIC AND RELATED ADIMNISTRATIVE AREAS. DEMO EXISTING INTERIOR STAIR, OPENING IN THE WALL FOR NEW DOORS AND WINDOW, AND DEMO FLOORS TO INSTALL NEW ELEVATOR. ALSO INCLUDES SITE DEMO TO ACCOMMODATE NEW PATIO, NEW WINDOW/ DOOR AND STAIRS . ADDING AN OUTDOOR PATIO, STAIRS, AND AN INTERIOR ELEVATOR
Permit Issued
Issued on 3/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 SINA KHOSRAVI
Corrections Issued 11/14/2022 SINA KHOSRAVI
Quality Review Completed 11/23/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/19/2022 SINA KHOSRAVI
Applicant returned to address corrections 12/23/2022 SINA KHOSRAVI
Applicant returned to address corrections 1/31/2023 SINA KHOSRAVI
Applicant returned to address corrections 2/6/2023 SINA KHOSRAVI
Applicant returned to address corrections 3/14/2023 SINA KHOSRAVI
Plan Check Approved 3/15/2023 SINA KHOSRAVI
Issued 3/20/2023 APPLICANT
TCO Issued (Expire Date: 03-20-2024) 9/22/2023 ERNESTO CORRAL
CofO in Progress 1/12/2024 KATY RAMIREZ
CofO Issued 1/19/2024 ADAM BURGESS
Permit Finaled 1/19/2024 ADAM BURGESS

Permit Application Clearance Information

Green Code Cleared 11/12/2022 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 11/28/2022 WALLIE JONG
Sewer availability Cleared 11/28/2022 WALLIE JONG
DAS Clearance Cleared 12/1/2022 Jesse Jimenez
Roof/Waste drainage to street Cleared 12/2/2022 WALLIE JONG
Hydrant and Access approval Cleared 12/14/2022 KURT CORRAL
Food establishment approval Cleared 12/27/2022 LACDHS APPROVED
Grading Pre-Inspection Cleared 2/9/2023 ALEXANDER HELFER
Fire Marshal Fire Life Safety Cleared 2/28/2023 MENOA AGHAJANI
GPI Written Notices Cleared 3/14/2023 SINA KHOSRAVI

Contact Information

Architect Morris,, Peter Lloyd; Lic. No.: NA32096       ,
Contractor Bergman Kprs Llc; Lic. No.: 982577-B 2850 SATURN STREET      BREA, CA 92821
Engineer Chen,, Jeff Y; Lic. No.: S4699 17500 REDHILL AVENUE SUITE 240      IRVINE, CA 92614

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/23/2023 Corrections Issued RAMAZANALI ALMASI
Footing/Foundation/Slab 3/23/2023 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Barrier 3/23/2023 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Subgrade 3/23/2023 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/24/2023 Approved RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/24/2023 Approved RAMAZANALI ALMASI
Reinforced Concrete Frame 3/24/2023 Approved RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 3/28/2023 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Steel/Welding 3/31/2023 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 3/31/2023 Partial Inspection KATY RAMIREZ
Deputy Reinf. Masonry 4/11/2023 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 4/11/2023 Conditional Approval KATY RAMIREZ
Green Building Rough 4/11/2023 Approved KATY RAMIREZ
Reinforced Masonry Frame 4/11/2023 Partial Approval KATY RAMIREZ
Deputy Reinf. Masonry 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 4/19/2023 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 4/19/2023 Partial Approval RAFAEL CORTES
Reinforced Concrete Frame 4/19/2023 Partial Approval RAFAEL CORTES
Deputy Drilled-In Anchors 4/24/2023 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/24/2023 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 4/24/2023 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 4/24/2023 Not Ready for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 4/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 4/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/5/2023 Conditional Approval KATY RAMIREZ
Deputy Reinf. Masonry 5/5/2023 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/5/2023 Conditional Approval KATY RAMIREZ
Special/Order Compliance 5/5/2023 Partial Inspection KATY RAMIREZ
Structural Steel Frame 5/10/2023 Conditional Approval VAHE KELEDJIAN
Deputy Steel/Welding 5/19/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 5/19/2023 Corrections Issued RAMAZANALI ALMASI
Insulation 5/22/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 5/22/2023 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 5/23/2023 Not Ready for Inspection RAMAZANALI ALMASI
Structural Steel Frame 5/23/2023 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Reinf. Masonry 5/25/2023 Approved RAMAZANALI ALMASI
Deputy Steel/Welding 5/25/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 5/25/2023 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 5/25/2023 Approved RAMAZANALI ALMASI
Deputy Reinf. Masonry 5/26/2023 Approved RAMAZANALI ALMASI
Deputy Steel/Welding 5/26/2023 Approved RAMAZANALI ALMASI
Footing/Foundation/Slab 5/26/2023 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 5/26/2023 Approved RAMAZANALI ALMASI
Structural Steel Frame 5/26/2023 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 5/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/31/2023 Approved RAMAZANALI ALMASI
Deputy Steel/Welding 5/31/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 5/31/2023 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 5/31/2023 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 5/31/2023 Approved RAMAZANALI ALMASI
Structural Steel Frame 5/31/2023 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Reinf. Concrete 6/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 6/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 6/2/2023 Conditional Approval MICHAEL ROSENBERG
Structural Steel Frame 6/2/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 6/5/2023 Partial Approval RAMAZANALI ALMASI
Insulation 6/5/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 6/6/2023 Not Ready for Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 6/6/2023 Not Ready for Inspection RAMAZANALI ALMASI
Structural Steel Frame 6/6/2023 Partial Approval RAMAZANALI ALMASI
Deputy Steel/Welding 6/7/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 6/8/2023 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 6/8/2023 Partial Approval KATY RAMIREZ
Structural Steel Frame 6/8/2023 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/9/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 6/12/2023 Partial Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 6/13/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 6/13/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 6/16/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 6/21/2023 Not Ready for Inspection KATY RAMIREZ
Structural Steel Frame 6/21/2023 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 6/22/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 6/27/2023 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 6/27/2023 Partial Approval ALFREDO LOPEZ
Insulation 6/28/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 6/29/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 6/29/2023 Approved RAMAZANALI ALMASI
Insulation 6/30/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 6/30/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 7/6/2023 Partial Approval RAMAZANALI ALMASI
Insulation 7/6/2023 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 7/6/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 7/10/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 7/11/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 7/11/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 7/12/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 7/13/2023 Partial Approval RAMAZANALI ALMASI
Pre-Inspection 7/17/2023 Partial Inspection KATY RAMIREZ
Special/Order Compliance 7/17/2023 Partial Inspection RAMAZANALI ALMASI
Deputy Steel/Welding 7/19/2023 Conditional Approval KATY RAMIREZ
Piling/Pier/Caisson 7/19/2023 Corrections Issued KATY RAMIREZ
Footing/Foundation/Slab 7/25/2023 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 7/27/2023 Partial Approval RAMAZANALI ALMASI
T-Bar Ceiling 8/2/2023 Not Ready for Inspection RAMAZANALI ALMASI
T-Bar Ceiling 8/7/2023 Not Ready for Inspection RAMAZANALI ALMASI
T-Bar Ceiling 8/8/2023 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Fireproofing 8/9/2023 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 8/10/2023 Conditional Approval RAMAZANALI ALMASI
T-Bar Ceiling 8/10/2023 Approved RAMAZANALI ALMASI
Deputy Fireproofing 8/11/2023 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 8/15/2023 Not Ready for Inspection RAMAZANALI ALMASI
Structural Steel Frame 8/15/2023 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Reinf. Concrete 8/16/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Steel/Welding 8/16/2023 Conditional Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 8/16/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 8/16/2023 Partial Approval RAMAZANALI ALMASI
Structural Steel Frame 8/16/2023 Off-Hour Fees Due
Structural Steel Frame 8/16/2023 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 8/17/2023 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 8/21/2023 Not Ready for Inspection ALAN MORELOS
Structural Steel Frame 8/21/2023 Partial Inspection ALAN MORELOS
Final 9/1/2023 Not Ready for Inspection KATY RAMIREZ
Final 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Final 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Reinforced Masonry Frame 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Special/Order Compliance 9/22/2023 Partial Approval KATY RAMIREZ
Final 12/15/2023 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 12/15/2023 Not Ready for Inspection KATY RAMIREZ
Green Building Final 12/15/2023 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 12/15/2023 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 12/15/2023 Not Ready for Inspection KATY RAMIREZ
Final 12/22/2023 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 12/22/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 12/22/2023 Not Ready for Inspection JEROME BLACKWOOD
Reinforced Masonry Frame 12/22/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 12/22/2023 Approved JEROME BLACKWOOD
Final 1/4/2024 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 1/4/2024 Approved KATY RAMIREZ
Green Building Final 1/4/2024 Approved KATY RAMIREZ
Reinforced Masonry Frame 1/4/2024 Approved KATY RAMIREZ
Final 1/12/2024 OK to Issue CofO KATY RAMIREZ