Excavation/Setback/Form/Re-Bar
|
3/23/2023
|
Corrections Issued
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
3/23/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
METHANE-Barrier
|
3/23/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
METHANE-Subgrade
|
3/23/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Drilled-In Anchors
|
3/24/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
3/24/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Reinforced Concrete Frame
|
3/24/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Excavation/Setback/Form/Re-Bar
|
3/28/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
3/31/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/31/2023
|
Partial Inspection
|
KATY RAMIREZ
|
|
Deputy Reinf. Masonry
|
4/11/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Steel/Welding
|
4/11/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Green Building Rough
|
4/11/2023
|
Approved
|
KATY RAMIREZ
|
|
Reinforced Masonry Frame
|
4/11/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Masonry
|
4/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/19/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
4/19/2023
|
Partial Approval
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
4/19/2023
|
Partial Approval
|
RAFAEL CORTES
|
|
Deputy Drilled-In Anchors
|
4/24/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Steel/Welding
|
4/24/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Footing/Foundation/Slab
|
4/24/2023
|
Corrections Issued
|
KATY RAMIREZ
|
|
Light Gage Steel Frame
|
4/24/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
4/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
5/1/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
5/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
5/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
5/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
5/3/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
5/3/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
5/3/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
5/4/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
5/4/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
5/4/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
5/5/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Masonry
|
5/5/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Steel/Welding
|
5/5/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Special/Order Compliance
|
5/5/2023
|
Partial Inspection
|
KATY RAMIREZ
|
|
Structural Steel Frame
|
5/10/2023
|
Conditional Approval
|
VAHE KELEDJIAN
|
|
Deputy Steel/Welding
|
5/19/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
5/19/2023
|
Corrections Issued
|
RAMAZANALI ALMASI
|
|
Insulation
|
5/22/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
5/22/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Masonry Wall/Backfill
|
5/23/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
5/23/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Masonry
|
5/25/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
5/25/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
5/25/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Masonry Wall/Backfill
|
5/25/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Masonry
|
5/26/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
5/26/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
5/26/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Masonry Wall/Backfill
|
5/26/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
5/26/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
5/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
5/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
5/31/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
5/31/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
5/31/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
5/31/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
5/31/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
5/31/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
6/1/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
6/1/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
6/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
6/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Structural Steel Frame
|
6/2/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
6/5/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Insulation
|
6/5/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
6/6/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
6/6/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
6/6/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
6/7/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Drywall Nailing
|
6/8/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/8/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Structural Steel Frame
|
6/8/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
6/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Masonry Wall/Backfill
|
6/12/2023
|
Partial Inspection
|
KATY RAMIREZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/13/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Light Gage Steel Frame
|
6/13/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Drywall Nailing
|
6/16/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Light Gage Steel Frame
|
6/21/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Structural Steel Frame
|
6/21/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Light Gage Steel Frame
|
6/22/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Drywall Nailing
|
6/27/2023
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Light Gage Steel Frame
|
6/27/2023
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Insulation
|
6/28/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
6/29/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
6/29/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Insulation
|
6/30/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
6/30/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
7/6/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Insulation
|
7/6/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Masonry Wall/Backfill
|
7/6/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Interior/Exterior Lathing
|
7/10/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
7/11/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Interior/Exterior Lathing
|
7/11/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
7/12/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
7/13/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Pre-Inspection
|
7/17/2023
|
Partial Inspection
|
KATY RAMIREZ
|
|
Special/Order Compliance
|
7/17/2023
|
Partial Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
7/19/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Piling/Pier/Caisson
|
7/19/2023
|
Corrections Issued
|
KATY RAMIREZ
|
|
Footing/Foundation/Slab
|
7/25/2023
|
Partial Inspection
|
KATY RAMIREZ
|
|
Footing/Foundation/Slab
|
7/27/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
T-Bar Ceiling
|
8/2/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
T-Bar Ceiling
|
8/7/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
T-Bar Ceiling
|
8/8/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Fireproofing
|
8/9/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Fireproofing
|
8/10/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
T-Bar Ceiling
|
8/10/2023
|
Approved
|
RAMAZANALI ALMASI
|
|
Deputy Fireproofing
|
8/11/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/15/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
8/15/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
8/16/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
8/16/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2023
|
Off-Hour Fees Due
|
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
8/16/2023
|
Off-Hour Fees Due
|
|
|
Structural Steel Frame
|
8/16/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
8/17/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Excavation/Setback/Form/Re-Bar
|
8/21/2023
|
Not Ready for Inspection
|
ALAN MORELOS
|
|
Structural Steel Frame
|
8/21/2023
|
Partial Inspection
|
ALAN MORELOS
|
|
Final
|
9/1/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Final
|
9/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
9/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Green Building Final
|
9/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
METHANE-Final
|
9/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Reinforced Masonry Frame
|
9/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
SGSOV-Seismic Gas S/O Valve
|
9/11/2023
|
SGSOV Not Ready
|
RAMAZANALI ALMASI
|
|
Smoke Detectors
|
9/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Special/Order Compliance
|
9/22/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Final
|
12/15/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Footing/Foundation/Slab
|
12/15/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Green Building Final
|
12/15/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Reinforced Masonry Frame
|
12/15/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
SGSOV-Seismic Gas S/O Valve
|
12/15/2023
|
SGSOV Not Ready
|
KATY RAMIREZ
|
|
Smoke Detectors
|
12/15/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Final
|
12/22/2023
|
Not Ready for Inspection
|
JEROME BLACKWOOD
|
|
Footing/Foundation/Slab
|
12/22/2023
|
Not Ready for Inspection
|
JEROME BLACKWOOD
|
|
Green Building Final
|
12/22/2023
|
Not Ready for Inspection
|
JEROME BLACKWOOD
|
|
Reinforced Masonry Frame
|
12/22/2023
|
Not Ready for Inspection
|
JEROME BLACKWOOD
|
|
SGSOV-Seismic Gas S/O Valve
|
12/22/2023
|
SGSOV Approved
|
JEROME BLACKWOOD
|
|
Smoke Detectors
|
12/22/2023
|
Approved
|
JEROME BLACKWOOD
|
|
Final
|
1/4/2024
|
Partial Inspection
|
KATY RAMIREZ
|
|
Footing/Foundation/Slab
|
1/4/2024
|
Approved
|
KATY RAMIREZ
|
|
Green Building Final
|
1/4/2024
|
Approved
|
KATY RAMIREZ
|
|
Reinforced Masonry Frame
|
1/4/2024
|
Approved
|
KATY RAMIREZ
|
|
Final
|
1/12/2024
|
OK to Issue CofO
|
KATY RAMIREZ
|