3005 S STONER AVE 90066

Certificate Information: 3005 S STONER AVE 90066

Application / Permit
22014-10000-05386
Plan Check / Job No.
B22LA22095
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Garage addition to existing two story dwelling
Permit Issued
Issued on 7/5/2024
Issuing Office
Current Status
Issued on 7/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 JOE VO
Corrections Issued 11/26/2022 JOE VO
Quality Review Completed 11/28/2022 GARO TELMI
Applicant returned to address corrections 1/8/2024 JOE VO
Plan Check Approved 7/1/2024 JOE VO
Issued 7/5/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/24/2023 JASON NG
Low Impact Development Cleared 7/25/2023 ROGELIO CORTES
Grading Pre-Inspection Cleared 1/8/2024 JOE VO
Roof/Waste drainage to street Cleared 6/18/2024 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: NA93049       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2024 Corrections Issued DANIEL VERA
Deputy Drilled-In Anchors 11/18/2024 Conditional Approval DANIEL VERA
Footing/Foundation/Slab 11/27/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 6/25/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Approved WILBER ROSALES
ELECTRICAL-Final 8/28/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 8/28/2025 Approved MICHAEL ALLEN
Drywall Nailing 9/25/2025 Approved KIRK SANDERS
ELECTRICAL-Final 9/25/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 1/22/2026 Approved ARAM AVEDISIAN
Final 1/22/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/22/2026 Approved ARAM AVEDISIAN
Green Building Rough 1/22/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 1/22/2026 Not Ready for Inspection ARAM AVEDISIAN