5127 N EL RIO AVE 90041
Certificate Information: 5127 N EL RIO AVE 90041
- Application / Permit
- 22014-10000-05385
- Plan Check / Job No.
- B22LA22094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) 348 SQ FT. DETACHED GARAGE TO ADU AND ADDITION (116 SF) PER LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2022 | VIVIAN LAO |
| Corrections Issued | 11/9/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 12/15/2022 | VIVIAN LAO |
| Plan Check Approved | 3/24/2023 | ANDREW SANTIAGO |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 4/2/2024 | CRAIG VAUGHAN |
| Permit Finaled | 4/8/2024 | DEROLD HAUFF |
| CofO Issued | 4/8/2024 | DEROLD HAUFF |
| Permit Finaled | 4/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 11/19/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 11/22/2022 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 12/12/2022 | KIRK LINKLATER |
| Construction within easement | Cleared | 3/17/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rivera,, Bobby Zulueta; Lic. No.: C77218 | 14703 HELWIG AVE NORWALK, CA 90650 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/16/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 10/4/2023 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/5/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/17/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/3/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/9/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/15/2023 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/15/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 11/15/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/15/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 11/17/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/27/2023 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | ROY SPAULDING |
| HVAC-Rough | 11/27/2023 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 11/27/2023 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/1/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/8/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/8/2023 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 12/8/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/8/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/13/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 12/13/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/13/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 12/20/2023 | Approved | BRENDAN MORELLI |
| Pre-Inspection | 12/20/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/29/2023 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 2/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/16/2024 | Corrections Issued | CRAIG VAUGHAN |
| Final | 3/8/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 3/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/13/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 3/13/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/13/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/28/2024 | Approved | CRAIG VAUGHAN |
| Final | 3/28/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| Green Building Final | 3/28/2024 | Approved | CRAIG VAUGHAN |