2691 1/2 W WAVERLY DR 90039

Certificate Information: 2691 1/2 W WAVERLY DR 90039

Application / Permit
22014-10000-05379
Plan Check / Job No.
B22LA22066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan Converting existing 3-car garage plus addition to ADU per LAMC 12.22A.33 (c) and (e)
Permit Issued
Issued on 4/20/2023
Issuing Office
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 MARCELA FRANQUEZ
Corrections Issued 11/30/2022 MARCELA FRANQUEZ
Quality Review Completed 12/13/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 4/20/2023 MARCELA FRANQUEZ
Issued 4/20/2023 APPLICANT
CofO in Progress 3/23/2024 THOMAS LOGRASSO
No Progress 3/23/2024 THOMAS LOGRASSO
CofO in Progress 4/2/2024 THOMAS LOGRASSO
CofO Issued 4/8/2024 DEROLD HAUFF
Permit Finaled 4/8/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 3/14/2023 JAZMIN ROQUE
Roof/Waste drainage to street Cleared 3/15/2023 STEVE MELGAR
Grading Pre-Inspection Cleared 3/16/2023 KIRK LINKLATER
Address approval Cleared 3/21/2023 STEVE MELGAR
Sewer availability Cleared 3/21/2023 STEVE MELGAR
Tenant Habitability Plan Cleared 3/21/2023 ISMAEL HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/22/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Foroughikia,, Babak; Lic. No.: C94091 21930 MARYLEE ST APT 87      WOODLAND HILLS, CA 91367

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2023 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 5/30/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/31/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 6/5/2023 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 8/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 8/9/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Rough 8/9/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/30/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 8/30/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 9/6/2023 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 9/26/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 10/10/2023 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 10/10/2023 Partial Approval JOSEPH MCGARRY
HVAC-Rough 10/10/2023 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/10/2023 Approved JOSEPH MCGARRY
Insulation 10/16/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/26/2023 Corrections Issued THOMAS LOGRASSO
Insulation 10/26/2023 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 10/26/2023 Partial Approval THOMAS LOGRASSO
Drywall Nailing 11/21/2023 Approved THOMAS LOGRASSO
Green Building Rough 11/21/2023 Approved THOMAS LOGRASSO
Final 3/6/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 3/14/2024 Conditional Approval THOMAS LOGRASSO
Final 3/14/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 3/14/2024 Approved THOMAS LOGRASSO
Green Building Final 3/14/2024 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 3/14/2024 Approved THOMAS LOGRASSO
Final 3/19/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 3/22/2024 Approved THOMAS LOGRASSO
Final 3/22/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 3/22/2024 Approved THOMAS LOGRASSO
Special/Order Compliance 3/26/2024 Corrections Issued THOMAS LOGRASSO
Final 4/2/2024 OK to Issue CofO THOMAS LOGRASSO