7924 S TRUXTON AVE 90045

Certificate Information: 7924 S TRUXTON AVE 90045

Application / Permit
22014-10000-05376
Plan Check / Job No.
B22LA22061
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Existing detached garage convert to an ADU with 198 SQFT addition. per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/17/2023
Issuing Office
Current Status
CofO Issued on 1/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 MOHAMMAD ESMAILI
Corrections Issued 11/8/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/7/2022 MOHAMMAD ESMAILI
Plan Check Approved 2/16/2023 MOHAMMAD ESMAILI
Issued 2/17/2023 APPLICANT
CofO in Progress 1/26/2025 TEMISTOCLES CAAL
Permit Finaled 1/30/2025 RICHARD STEINBACH
Permit Finaled 1/30/2025 RICHARD STEINBACH
CofO Issued 1/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 12/7/2022 FREDDY GARCIA
Address approval Cleared 12/21/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 12/21/2022 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 12/21/2022 AHMED AMARRAGY
Sewer availability Cleared 12/21/2022 AHMED AMARRAGY
Construction within easement Cleared 2/13/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673
Engineer Standley,, Craig Erick; Lic. No.: NA87675       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/1/2023 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 3/1/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 3/1/2023 Not Ready for Inspection HERBERT GIRON
Wood Frame 3/1/2023 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 11/2/2023 Approved BOBBY KEY
PLUMBING-Rough 11/2/2023 Partial Approval BOBBY KEY
Wood Frame 12/6/2023 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 12/19/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 12/19/2023 Approved BOBBY KEY
ELECTRICAL-Rough 1/12/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved BOBBY KEY
Green Building Rough 1/12/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 1/12/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 2/23/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 2/23/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/23/2024 Partial Approval TEMISTOCLES CAAL
Insulation 2/26/2024 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/20/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 3/20/2024 Approved TEMISTOCLES CAAL
Green Building Rough 3/20/2024 Approved TEMISTOCLES CAAL
Insulation 3/20/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 4/30/2024 Partial Inspection HERBERT GIRON
Special/Order Compliance 4/30/2024 Partial Inspection TEMISTOCLES CAAL
Underground Mechanical 4/30/2024 Partial Approval BOBBY KEY
ELECTRICAL-Final 5/28/2024 Not Ready for Inspection BOBBY KEY
Final 5/28/2024 Corrections Issued BOBBY KEY
Green Building Final 5/28/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 5/28/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 5/28/2024 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 5/28/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 7/9/2024 Not Ready for Inspection BOBBY KEY
Final 7/9/2024 Corrections Issued BOBBY KEY
Green Building Final 7/9/2024 Approved BOBBY KEY
HVAC-Final 7/9/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 7/9/2024 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 7/9/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready TEMISTOCLES CAAL
ELECTRICAL-Final 11/26/2024 Corrections Issued BOBBY KEY
Final 11/26/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/26/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 11/26/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Not Ready BOBBY KEY
ELECTRICAL-Final 1/16/2025 Corrections Issued TEMISTOCLES CAAL
Final 1/16/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 1/16/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 1/16/2025 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Approved TEMISTOCLES CAAL
ELECTRICAL-Final 1/24/2025 Approved TEMISTOCLES CAAL
Final 1/24/2025 OK to Issue CofO TEMISTOCLES CAAL
HVAC-Final 1/24/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 1/24/2025 Approved TEMISTOCLES CAAL