2807 W ESTARA AVE 90065

Certificate Information: 2807 W ESTARA AVE 90065

Application / Permit
22014-10000-05362
Plan Check / Job No.
B22LA21989
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to ADU with addition and connect it to another (E) detached garage per LAMC 12.22 A.33 (c)-(d). All work done per engineering.
Permit Issued
Issued on 11/13/2023
Issuing Office
Metro
Current Status
Issued on 11/13/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2022 APPLICANT
Assigned to Plan Check Engineer 11/7/2022 VICTOR CHEN
Corrections Issued 11/17/2022 VICTOR CHEN
Building Plans Picked Up 11/18/2022 APPLICANT
Applicant returned to address corrections 4/5/2023 GEORGE ALVAREZ
Plan Check Approved 5/30/2023 DANIEL SMILEY
Issued 11/13/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/27/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 1/10/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 1/10/2023 CHRISTOPHER ROCHA
Grading Pre-Inspection Cleared 1/23/2023 KIRK LINKLATER
Community Plan Implem. Overlay Cleared 2/15/2023 NASHYA JENSEN
Supp. Use District POD/CDO/TDO Cleared 2/15/2023 NASHYA JENSEN
ZI Cleared 2/15/2023 NASHYA JENSEN
Low Impact Development Cleared 2/21/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 2/21/2023 CINDY QI
GPI Written Notices Cleared 4/5/2023 VICTOR CHEN
Construction near power lines Cleared 5/26/2023 RIDWAN HARDY

Contact Information

Architect Lee,, Joong H; Lic. No.: C26271 6721 VALMONT STREET      TUJUNGA, CA 91042
Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/19/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/3/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/9/2024 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 5/31/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 5/31/2024 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 6/3/2024 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 6/4/2024 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 6/4/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/10/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 6/10/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 6/10/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 6/13/2024 Conditional Approval THOMAS LOGRASSO
Insulation 6/13/2024 Not Ready for Inspection THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 6/13/2024 Corrections Issued THOMAS LOGRASSO
Insulation 6/21/2024 Approved WILLIAM KUEHN
Drywall Nailing 7/1/2024 Corrections Issued BRENDAN MORELLI
Drywall Nailing 7/12/2024 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/5/2024 Approved THOMAS LOGRASSO
Drywall Nailing 9/5/2024 Approved THOMAS LOGRASSO
Green Building Rough 9/5/2024 Approved THOMAS LOGRASSO
MERV13>=Rough 9/5/2024 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 9/5/2024 Approved THOMAS LOGRASSO
Final 10/25/2024 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 10/25/2024 Approved THOMAS LOGRASSO
Smoke Detectors 10/25/2024 Approved THOMAS LOGRASSO
Final 11/15/2024 Corrections Issued THOMAS LOGRASSO
Final 12/16/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 12/16/2024 Approved THOMAS LOGRASSO