140 S ALTA VISTA BLVD 90036
Certificate Information: 140 S ALTA VISTA BLVD 90036
- Application / Permit
- 22014-10000-05351
- Plan Check / Job No.
- B22LA21960
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH ADDITION ( 5' X 7' ) TO REAR FOR EGRESS PER CA GOVT. STATE CODE 65852.2(e)(1)(A). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 9/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | ROSENDO MEDINA |
| Corrections Issued | 11/8/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/7/2023 | ROSENDO MEDINA |
| Plan Check Approved | 4/27/2023 | ROSENDO MEDINA |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 9/6/2024 | JOSE MACIAS |
| CofO Issued | 9/19/2024 | DEROLD HAUFF |
| Permit Finaled | 9/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 11/14/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | JEANIE LAM |
| Sewer availability | Cleared | 11/15/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 3/7/2023 | TINA MIRANDA |
| HPOZ | Cleared | 4/6/2023 | DAMIAN GATTO |
Contact Information
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | , |
| Engineer | Mercado,, Lizandro; Lic. No.: NA4331 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2023 | Corrections Issued | LILIANA PORTILLO |
| METHANE-Barrier | 6/14/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 6/14/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 6/14/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 6/22/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 7/7/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/7/2023 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/14/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/27/2023 | Approved | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Approved | CHARLES BOGHOSKHAN |
| HVAC-Rough | 10/27/2023 | Conditional Approval | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 10/27/2023 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 11/1/2023 | Conditional Approval | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 11/1/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 11/1/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/18/2024 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/26/2024 | Approved | LILIANA PORTILLO |
| Insulation | 4/9/2024 | Corrections Issued | AMIR NAZARIAN |
| Insulation | 4/11/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 4/15/2024 | Approved | AMIR NAZARIAN |
| Gas Test | 8/6/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 8/12/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Final | 8/12/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 8/13/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 8/22/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | AMIR NAZARIAN |
| Final | 8/23/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 8/23/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 8/23/2024 | Approved | AMIR NAZARIAN |
| METHANE-Final | 8/23/2024 | Approved | AMIR NAZARIAN |
| METHANE-Rough | 8/23/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 8/23/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 8/28/2024 | Approved | AMIR NAZARIAN |
| Final | 8/29/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/29/2024 | Approved | ENRIQUE MIRELES |
| Final | 9/4/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 9/4/2024 | Approved | JOSE MACIAS |