1071-1071 1/2 E MARCO PL 90291

Certificate Information: 1071-1071 1/2 E MARCO PL 90291

Application / Permit
22014-10000-05345
Plan Check / Job No.
B22LA21925
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel (E) SFD, including second story addition, new attached garage, and an attached ADU.
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofO Issued on 3/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 HELEN NGUYEN
Corrections Issued 11/8/2022 VIVIAN LAO
Quality Review Completed 11/10/2022 KEN GILL
Building Plans Picked Up 11/14/2022 APPLICANT
Applicant returned to address corrections 12/29/2022 HELEN NGUYEN
Applicant returned to address corrections 1/5/2023 HELEN NGUYEN
Plan Check Approved 1/18/2023 HELEN NGUYEN
Issued 1/20/2023 APPLICANT
CofO in Progress 3/15/2024 HERBERT GIRON
Permit Finaled 3/19/2024 DANIEL ORRANTE
CofO Issued 3/19/2024 DANIEL ORRANTE
Permit Finaled 3/19/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 12/1/2022 RAYMOND MUGAMBWA
Address approval Cleared 12/6/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 12/7/2022 ANTHONY MAINEZ
Sewer availability Cleared 12/7/2022 ANTHONY MAINEZ
Low Impact Development Cleared 12/12/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/12/2022 ANTHONY MAINEZ
Specific Plan Cleared 12/29/2022 JOSHUA JONES
Permit Cleared 1/17/2023 ANTHONY MAINEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Zepeda Juan; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/7/2023 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/7/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 4/7/2023 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 4/17/2023 Approved EVAN COOPER
Footing/Foundation/Slab 4/17/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval EVAN COOPER
HVAC-Rough 7/24/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 7/24/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 7/25/2023 Approved EVAN COOPER
ELECTRICAL-Rough 7/26/2023 Approved EVAN COOPER
HVAC-Rough 7/26/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 7/26/2023 Approved EVAN COOPER
Deputy Steel/Welding 7/28/2023 Conditional Approval EVAN COOPER
Interior/Exterior Lathing 8/3/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 8/14/2023 Corrections Issued HERBERT GIRON
Green Building Rough 8/14/2023 Conditional Approval HERBERT GIRON
Verify Sprinkler Sign Off 8/14/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/18/2023 Partial Approval HERBERT GIRON
Green Building Rough 8/18/2023 Approved HERBERT GIRON
HVAC-Rough 8/18/2023 Not Ready for Inspection HERBERT GIRON
Insulation 8/18/2023 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 8/23/2023 Approved HERBERT GIRON
HVAC-Rough 8/23/2023 Not Ready for Inspection HERBERT GIRON
Insulation 8/23/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 8/28/2023 Not Ready for Inspection HERBERT GIRON
Insulation 8/28/2023 Approved HERBERT GIRON
Drywall Nailing 9/5/2023 Approved HERBERT GIRON
HVAC-Rough 9/5/2023 Approved HERBERT GIRON
Shower Pan 9/28/2023 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 10/26/2023 Approved HERBERT GIRON
ELECTRICAL-Final 2/29/2024 Corrections Issued HERBERT GIRON
HVAC-Final 2/29/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/29/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 2/29/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/8/2024 Not Ready for Inspection HERBERT GIRON
Gas Test 3/8/2024 Approved HERBERT GIRON
HVAC-Final 3/8/2024 Approved HERBERT GIRON
PLUMBING-Final 3/8/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/13/2024 Corrections Issued HERBERT GIRON
Final 3/13/2024 Corrections Issued HERBERT GIRON
Green Building Final 3/13/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/15/2024 Approved HERBERT GIRON
Final 3/15/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 3/15/2024 Approved HERBERT GIRON