418 N ALFRED ST 90048

Certificate Information: 418 N ALFRED ST 90048

Application / Permit
22014-10000-05324
Plan Check / Job No.
B22LA21836
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: 16' 2" X 9' 7" SIDE ADDITION TO (E) DUPLEX AND REMODEL TO ADD (1) BEDROOM/BATHROOM & REVISE ENTIRE FLOOR PLAN LAYOUT OF DUPLEX UNIT #2. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/15/2023
Issuing Office
Current Status
Issued on 2/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 GURUNATH NESARAJAH
Corrections Issued 11/11/2022 GURUNATH NESARAJAH
Plan Check Approved 1/31/2023 GURUNATH NESARAJAH
No Progress 2/14/2023 GURUNATH NESARAJAH
Plan Check Approved 2/14/2023 GURUNATH NESARAJAH
Issued 2/15/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/5/2023 CINDY QI
Sewer availability Cleared 1/5/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/9/2023 CINDY QI

Contact Information

Architect Hellman,, Carey Philip; Lic. No.: NA10510       ,
Contractor Owner-Builder       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 2/22/2023 Approved MICHAEL LEWIS
METHANE-Barrier 2/22/2023 Approved MICHAEL LEWIS
METHANE-Subgrade 2/22/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Not Ready for Inspection MICHAEL LEWIS
Wood Frame 3/2/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 3/7/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved MICHAEL LEWIS
Insulation 3/9/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval MICHAEL LEWIS
METHANE-Rough 4/13/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 4/13/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 4/26/2023 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Rough 5/1/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 5/19/2023 Approved LILIANA PORTILLO
Shower Pan 5/19/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/30/2023 Not Ready for Inspection LILIANA PORTILLO
Final 8/30/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 8/30/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 8/30/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 8/30/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 9/8/2023 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 11/8/2023 Approved LILIANA PORTILLO
Final 11/8/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 11/8/2023 Approved LILIANA PORTILLO
Green Building Rough 11/8/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 11/8/2023 Approved LILIANA PORTILLO