10459 N ILEX AVE 91331
Certificate Information: 10459 N ILEX AVE 91331
- Application / Permit
- 22014-10000-05318
- Plan Check / Job No.
- B22LA21795
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and convert (E) detached carport to ADU per LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 7/26/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | AUNG SOE |
| Corrections Issued | 11/8/2022 | AUNG SOE |
| Plan Check Approved | 3/7/2023 | SHANGQIN XIE |
| Issued | 7/26/2023 | APPLICANT |
| CofO in Progress | 2/16/2024 | MICHEL ABAJAN |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 11/17/2022 | KENTON TRINH |
| Address approval | Cleared | 11/18/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 11/18/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 2/13/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Jkc Construction & Design; Lic. No.: 1007078-B | 18880 WELLS DRIVE TARZANA, CA 91356 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Corrections Issued | MICHEL ABAJAN |
| Pre-Inspection | 8/30/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 9/5/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/5/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/25/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/25/2023 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 9/25/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 9/25/2023 | Approved | MICHEL ABAJAN |
| Insulation | 9/28/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 10/2/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/5/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/5/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/15/2024 | Approved | MICHEL ABAJAN |
| Final | 2/15/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/15/2024 | Approved | MICHEL ABAJAN |
| Green Building Final | 2/15/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 2/15/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/15/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 2/15/2024 | Approved | MICHEL ABAJAN |