600 N ENTRADA DR 90402
Certificate Information: 600 N ENTRADA DR 90402
- Application / Permit
- 22014-10000-05309
- Plan Check / Job No.
- B22LA21743
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 143 SQFT ADDITION TO 1ST FLOOR - ENLARGE LIVING ROOM, KITCHEN, DIMING, AN ENTRY. 645 SQFT ADDITION TO 2ND FLOOR NEW MASTER SUITE 788 TOTAL ADDITION
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/26/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | JAD BASMA |
| Corrections Issued | 11/21/2022 | JAD BASMA |
| Quality Review Completed | 12/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/7/2022 | APPLICANT |
| Plan Check Approved | 3/28/2023 | JAD BASMA |
| Issued | 10/26/2023 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/31/2023 | RUBEN VASQUEZ |
| BHO/Hillside ordinance | Cleared | 2/2/2023 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 2/2/2023 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 2/2/2023 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 2/2/2023 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 2/2/2023 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2023 | DENNIS BRAGIN |
| Sewer availability | Cleared | 2/2/2023 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 3/10/2023 | LAVEON RIDER |
| Low Impact Development | Cleared | 3/10/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/14/2023 | DENNIS BRAGIN |
| GPI Written Notices | Cleared | 3/28/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 3/28/2023 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 8/16/2024 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/8/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/26/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 5/9/2025 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 9/12/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 12/26/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 1/6/2026 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 1/6/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 1/12/2026 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 1/12/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 1/13/2026 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 1/13/2026 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 1/14/2026 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/5/2026 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/17/2026 | Partial Approval | HERBERT GIRON |
| Insulation | 3/17/2026 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/24/2026 | Approved | DANIEL VERA |
| Green Building Rough | 4/24/2026 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 4/24/2026 | Approved | DANIEL VERA |
| Insulation | 5/11/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 5/19/2026 | Approved | HERBERT GIRON |