1247 1/2 N EUBANK AVE 90744

Certificate Information: 1247 1/2 N EUBANK AVE 90744

Application / Permit
22014-10000-05306
Plan Check / Job No.
B22LA21733
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1-story New ADU addition to (E) detached garage per ordinance, All work per WFPP and Methane Method C
Permit Issued
Issued on 3/12/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 DANIEL SMILEY
Corrections Issued 11/4/2022 DANIEL SMILEY
Building Plans Picked Up 11/7/2022 APPLICANT
Applicant returned to address corrections 2/21/2023 JOSEPH RAFOLS
Applicant returned to address corrections 9/18/2023 VICTOR CHEN
Applicant returned to address corrections 3/8/2024 MINA HABILI
Plan Check Approved 3/12/2024 NEHEMIAS RAMOS
Issued 3/12/2024 APPLICANT
CofO in Progress 5/4/2026 EUGENE CASSIDY
Permit Finaled 5/8/2026 ANSON MAGLASANG
CofO Issued 5/8/2026 ANSON MAGLASANG
Permit Finaled 5/8/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/21/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 2/22/2023 ANA SORIANO
Sewer availability Cleared 10/5/2023 ERIK BEASLEY
Low Impact Development Cleared 3/6/2024 LUIS LUVANO
Tenant Habitability Plan Cleared 3/11/2024 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 3/12/2024 JILVER MAZARIEGOS

Contact Information

Contractor Construction & Drafting Services; Lic. No.: 918107-B 1243 1/2 ANAHEIM STREET      HARBOR CITY, CA 90710

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/28/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/5/2024 Approved JOSEPH MCGARRY
METHANE-Barrier 9/5/2024 Approved JOSEPH MCGARRY
METHANE-Subgrade 9/5/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 9/5/2024 Partial Approval JOSEPH MCGARRY
Sewer 9/5/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 1/7/2025 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Corrections Issued BEN MOLSTAD
Green Building Rough 1/7/2025 Not Ready for Inspection BEN MOLSTAD
METHANE-Rough 1/7/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 1/21/2025 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 2/6/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 2/6/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 3/13/2025 Approved EUGENE CASSIDY
Green Building Rough 3/13/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/13/2025 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 3/13/2025 Approved EUGENE CASSIDY
Insulation 3/28/2025 Partial Approval EUGENE CASSIDY
Drywall Nailing 4/21/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/15/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/5/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 9/5/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 9/9/2025 Approved EUGENE CASSIDY
PLUMBING-Final 9/9/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 10/3/2025 Approved EUGENE CASSIDY
PLUMBING-Final 10/3/2025 Approved EUGENE CASSIDY
Final 10/8/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 10/8/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 10/8/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 10/8/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/16/2026 Approved EUGENE CASSIDY
Final 3/16/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 3/16/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/13/2026 Approved EUGENE CASSIDY
Final 4/13/2026 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 4/13/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 5/4/2026 Approved EUGENE CASSIDY
Final 5/4/2026 OK to Issue CofO EUGENE CASSIDY