1247 1/2 N EUBANK AVE 90744
Certificate Information: 1247 1/2 N EUBANK AVE 90744
- Application / Permit
- 22014-10000-05306
- Plan Check / Job No.
- B22LA21733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1-story New ADU addition to (E) detached garage per ordinance, All work per WFPP and Methane Method C
- Permit Issued
- Issued on 3/12/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | DANIEL SMILEY |
| Corrections Issued | 11/4/2022 | DANIEL SMILEY |
| Building Plans Picked Up | 11/7/2022 | APPLICANT |
| Applicant returned to address corrections | 2/21/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 9/18/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 3/8/2024 | MINA HABILI |
| Plan Check Approved | 3/12/2024 | NEHEMIAS RAMOS |
| Issued | 3/12/2024 | APPLICANT |
| CofO in Progress | 5/4/2026 | EUGENE CASSIDY |
| Permit Finaled | 5/8/2026 | ANSON MAGLASANG |
| CofO Issued | 5/8/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/8/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/21/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | ANA SORIANO |
| Sewer availability | Cleared | 10/5/2023 | ERIK BEASLEY |
| Low Impact Development | Cleared | 3/6/2024 | LUIS LUVANO |
| Tenant Habitability Plan | Cleared | 3/11/2024 | RICARDO BOHORQUEZ |
| Roof/Waste drainage to street | Cleared | 3/12/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Construction & Drafting Services; Lic. No.: 918107-B | 1243 1/2 ANAHEIM STREET HARBOR CITY, CA 90710 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/28/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/5/2024 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 9/5/2024 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 9/5/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/5/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 9/5/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 1/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| METHANE-Rough | 1/7/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 1/21/2025 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 2/6/2025 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/13/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/13/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/13/2025 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 3/13/2025 | Approved | EUGENE CASSIDY |
| Insulation | 3/28/2025 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 4/21/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/15/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/5/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 9/5/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 9/9/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/9/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/3/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/3/2025 | Approved | EUGENE CASSIDY |
| Final | 10/8/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/8/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 10/8/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/8/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/16/2026 | Approved | EUGENE CASSIDY |
| Final | 3/16/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/16/2026 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/13/2026 | Approved | EUGENE CASSIDY |
| Final | 4/13/2026 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 4/13/2026 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/4/2026 | Approved | EUGENE CASSIDY |
| Final | 5/4/2026 | OK to Issue CofO | EUGENE CASSIDY |