5838 N SALOMA AVE 91411
Certificate Information: 5838 N SALOMA AVE 91411
- Application / Permit
- 22014-10000-05294
- Plan Check / Job No.
- B22LA21687
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EpLAN: CONVERT DETACHED GARAGE WITH ADDITION TO ADU
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Current Status
- CofO in Progress on 3/8/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2022 | DANIEL SANJUAN |
| Corrections Issued | 11/2/2022 | DANIEL SANJUAN |
| Plan Check Approved | 1/24/2023 | DANIEL SANJUAN |
| Issued | 1/24/2023 | APPLICANT |
| CofO in Progress | 11/16/2023 | RYAN SALAZAR |
| No Progress | 3/8/2024 | ROBERT GOLD |
| CofO in Progress | 3/8/2024 | ROBERT GOLD |
| CofO in Progress | 3/8/2024 | ROBERT GOLD |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2022 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | RYAN KIM |
| Sewer availability | Cleared | 11/9/2022 | RYAN KIM |
| Construction near power lines | Cleared | 1/18/2023 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Ha My Design, Inc; Lic. No.: 999603-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/6/2023 | Approved | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/6/2023 | Corrections Issued | ROBERT GOLD |
| Underground Mechanical | 3/6/2023 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 3/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/10/2023 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/10/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/10/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/21/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 6/21/2023 | Approved | RYAN SALAZAR |
| Insulation | 7/12/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/12/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/17/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 7/17/2023 | Approved | RYAN SALAZAR |
| Sewer | 7/17/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/6/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 11/6/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 11/6/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 11/6/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | RYAN SALAZAR |
| Final | 11/13/2023 | Conditional Approval | RYAN SALAZAR |
| Service/Power Release | 11/16/2023 | Approved | RYAN SALAZAR |
| Final | 3/8/2024 | Corrections Issued | ROBERT GOLD |