2621 S CATALINA ST 90007

Certificate Information: 2621 S CATALINA ST 90007

Application / Permit
22014-10000-05262
Plan Check / Job No.
B22LA21508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to ADU with addition to side of ADU per Ordinance LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/12/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 VICTOR CHEN
Corrections Issued 11/7/2022 VICTOR CHEN
Building Plans Picked Up 11/8/2022 APPLICANT
Plan Check Approved 4/4/2023 WEIJIAN HUANG
Issued 4/12/2023 APPLICANT
CofO in Progress 6/18/2025 WILLIAM SIERRA
Permit Finaled 6/22/2025 DEROLD HAUFF
CofO Issued 6/22/2025 DEROLD HAUFF
Permit Finaled 6/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/18/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 11/22/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 11/22/2022 CHRISTOPHER ROCHA
HPOZ Cleared 2/16/2023 JONATHAN KAPLAN
Low Impact Development Cleared 2/21/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 2/27/2023 AMAAN MALIK

Contact Information

Contractor Michael'S Construction Company Inc; Lic. No.: 793978-B 4689 EAGLE ROCK BLVD      LOS ANGELES, CA 90041
Engineer Tamu,, O C; Lic. No.: C29787 P O BOX 17083      LONG BEACH, CA 90807

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 5/17/2023 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 5/18/2023 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 6/1/2023 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 6/1/2023 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Barrier 6/1/2023 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 6/1/2023 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 6/16/2023 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 6/23/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/21/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/11/2023 Approved KATHRYN BUTTERWORTH
Underground Mechanical 9/11/2023 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 9/18/2023 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 9/18/2023 Approved KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 9/21/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 9/26/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/26/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 9/26/2023 Approved ALIZAH MAYAGOITIA
Insulation 10/16/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/16/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 10/19/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 10/25/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/25/2023 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 11/20/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/28/2023 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/22/2024 Approved JOSEPH MCGARRY
Final 7/22/2024 Corrections Issued JOSEPH MCGARRY
Gas Test 7/22/2024 Approved JOSEPH MCGARRY
Green Building Final 7/22/2024 Approved JOSEPH MCGARRY
Green Building Rough 7/22/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/22/2024 Approved JOSEPH MCGARRY
Pre-Inspection 4/14/2025 No Access for Inspection WILLIAM SIERRA
Final 6/17/2025 OK to Issue CofO WILLIAM SIERRA
Special/Order Compliance 6/17/2025 Partial Inspection OSVALDO PARAMO