8802 S LILIENTHAL AVE 90045
Certificate Information: 8802 S LILIENTHAL AVE 90045
- Application / Permit
- 22014-10000-05248
- Plan Check / Job No.
- B22LA21452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan ADU garage conversion with addition PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Current Status
- CofO Issued on 8/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2022 | JOHNPAUL ISIP |
| Corrections Issued | 11/2/2022 | JASON JANGADA |
| Applicant returned to address corrections | 11/30/2022 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 1/21/2023 | ALFREDO JARA |
| Plan Check Approved | 2/23/2023 | JOHNPAUL ISIP |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 8/14/2024 | BOBBY KEY |
| Permit Finaled | 8/15/2024 | RICHARD STEINBACH |
| CofO Issued | 8/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2023 | CATHERINE ADROVER |
| Sewer availability | Cleared | 1/17/2023 | CATHERINE ADROVER |
| Specific Plan | Cleared | 1/18/2023 | JOSHUA JONES |
| Roof/Waste drainage to street | Cleared | 1/19/2023 | CATHERINE ADROVER |
| Construction near power lines | Cleared | 2/13/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/26/2023 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 5/2/2023 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 5/2/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/5/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 8/25/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/13/2023 | Approved | BOBBY KEY |
| Green Building Rough | 9/13/2023 | Approved | BOBBY KEY |
| Insulation | 9/13/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 9/22/2023 | Approved | BOBBY KEY |
| Shower Pan | 10/24/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/7/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 11/7/2023 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 12/27/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/25/2024 | Approved | BOBBY KEY |
| Final | 6/25/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 6/25/2024 | Approved | BOBBY KEY |
| HVAC-Final | 6/25/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 6/25/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/25/2024 | Approved | BOBBY KEY |
| Final | 8/13/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/13/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Approved | BOBBY KEY |